Quotation for Kooragang Bulk Handling Pty Ltd · attn Peter Lam
CV-9 soft starter replacement
Q-26-0181 · issued 14 Oct 2026 · valid until 13 Nov 2026 · Berth K4 conveyor substation
| Item | Qty | Unit ex GST | Amount |
|---|---|---|---|
| Equipment & components | $14,415.80 | ||
| ABB-PSTX105 · ABB PSTX105-600-70 soft starter 55 kW | 1 ea | $3,342.80 | $3,342.80 |
| NHP-MCCB-250 · NHP 250 A 3P MCCB, 36 kA, electronic trip | 1 ea | $1,323.00 | $1,323.00 |
| RIT-VX-2008 · Rittal VX25 freestanding 2000H × 800W × 600D | 1 ea | $3,432.00 | $3,432.00 |
| CBL-95-4C · Cable 95 mm² 4C+E XLPE/PVC 0.6/1 kV | 60 m | $105.30 | $6,318.00 |
| Labour | $7,920.00 | ||
| Workshop labour | 26 hr | $115.00 | $2,990.00 |
| Site labour | 32 hr | $125.00 | $4,000.00 |
| Project management | 6 hr | $155.00 | $930.00 |
| Subtotal ex GST | $22,335.80 |
| GST | $2,233.58 |
| Total inc GST | $24,569.38 |
Lead time about 8 weeks from order. Excludes: Civil works, concrete plinths and trenching unless listed. Supply authority fees. Works outside normal hours unless agreed.