Quotation for Myall Coast Regional Council · attn Tim Hargreaves
SPS-22 pump station switchboard replacement
Q-26-0186 · issued 22 Oct 2026 · valid until 21 Nov 2026 · SPS-22 Lemon Tree Passage
| Item | Qty | Unit ex GST | Amount |
|---|---|---|---|
| DOL pump starter — up to 15 kW × 2 | $1,724.76 | ||
| NHP-MPCB-32 · Motor protection circuit breaker 25–32 A | 2 ea | $264.60 | $529.20 |
| NHP-CTR-40 · AC3 40 A contactor, 24 VDC coil | 2 ea | $226.80 | $453.60 |
| NHP-SEL-HOA · Hand-Off-Auto 3-position selector switch | 2 ea | $70.20 | $140.40 |
| NHP-PL-LED · LED pilot light 24 V (red / green / amber) | 6 ea | $35.10 | $210.60 |
| NHP-RLY-24 · Control relay 24 VDC 4 C/O c/w base | 4 ea | $45.90 | $183.60 |
| RX-TB-4 · Terminal block 4 mm², box of 50 | 2 ea | $89.90 | $179.80 |
| RX-DIN-35 · DIN rail 35 mm top-hat, 2 m length | 2 ea | $13.78 | $27.56 |
| Equipment & components | $11,193.20 | ||
| SE-TM241 · Schneider Modicon M241 PLC, 24 I/O, Ethernet + CANopen | 1 ea | $1,612.00 | $1,612.00 |
| TEL-RTU-4G · 4G telemetry RTU c/w antenna & SIM tray | 1 ea | $3,705.00 | $3,705.00 |
| RIT-SS316-1210 · 316 stainless enclosure 1200 × 1000 × 400, IP66 | 1 ea | $4,225.00 | $4,225.00 |
| EH-FMX21 · E+H Waterpilot FMX21 hydrostatic level 0–10 m, 20 m cable | 1 ea | $1,651.20 | $1,651.20 |
| Labour | $10,060.00 | ||
| Engineering & drafting | 14 hr | $145.00 | $2,030.00 |
| Workshop labour | 40 hr | $115.00 | $4,600.00 |
| Site labour | 20 hr | $125.00 | $2,500.00 |
| Project management | 6 hr | $155.00 | $930.00 |
| Subtotal ex GST | $22,977.96 |
| GST | $2,297.80 |
| Total inc GST | $25,275.76 |
Lead time about 8 weeks from order. Excludes: Civil works, concrete plinths and trenching unless listed. Supply authority fees. Works outside normal hours unless agreed.