Hydra Power Solutions Pty Ltd
5 Campbell Street, Tomago NSW 2322 · 1800 173 178 · info@hydrapowersolutions.com.au
ABN 62 631 448 207
Quotation
Q-26-0170
Date 10 Sep 2026
Valid until 10 Oct 2026
Lead time 9 weeks
Prepared by Daniel Reeves
Customer
Muswellbrook Quarry Products
Attn: Craig Duffy
Site: Denman Rd quarry — substation 2
455 Denman Road Muswellbrook NSW 2333
ABN 88 004 776 215
1.5 MVA transformer overhaul & oil sampling — Sub 2
Pricing
| Item | Qty | Unit ex GST | Amount |
| Labour | $18,050.00 |
| Strip, inspect, rebuild & reassemble | 110 hr | $115.00 | $12,650.00 |
| Removal, return & reconnection | 24 hr | $125.00 | $3,000.00 |
| Test reports | 8 hr | $145.00 | $1,160.00 |
| Project management | 8 hr | $155.00 | $1,240.00 |
| Other | $14,700.00 |
| Transformer oil — Nynas Nytro 1,200 L | 1 lot | $5,400.00 | $5,400.00 |
| Gasket set, bushings & breather | 1 lot | $3,800.00 | $3,800.00 |
| Oil analysis — DGA & furans (2 samples) | 1 lot | $1,900.00 | $1,900.00 |
| Low-loader transport both ways | 1 lot | $3,600.00 | $3,600.00 |
Exclusions
Civil works, concrete plinths and trenching unless listed. Supply authority fees. Works outside normal hours unless agreed.
Acceptance
To accept, sign below and return with your purchase order, or accept online using the link in our email.
Name: ______________________ Signature: ______________________ Date: ____________ PO number: ______________
Regards,
Daniel Reeves · Hydra Power Solutions Pty Ltd · 1800 173 178
| Subtotal (ex GST) | $32,750.00 |
| GST 10% | $3,275.00 |
| Total (inc GST) | $36,025.00 |
Prices are in Australian dollars and exclude GST unless shown. Payment terms: 30 days EOM from invoice, progress claims monthly against the stages of the job.