Hydra Power Solutions Pty Ltd
5 Campbell Street, Tomago NSW 2322 · 1800 173 178 · info@hydrapowersolutions.com.au
ABN 62 631 448 207
Progress claim
PC-26-036-02
Claim no. 2
Period to 31 Oct 2026
Job J-26-036
Your order BBD-0912
Claim to
Bowen Basin Dewatering Pty Ltd
Shane Keogh
8 Mill Street, Moranbah QLD 4744
ABN 29 618 774 330
4 × dewatering pumpset control panels (Flygt 2670) — Moranbah yard
| Description | Contract value | % complete | Claimed to date | Previous claims | This claim |
|---|---|---|---|---|---|
| Design & drawings | $4,480.63 | 100% | $4,480.63 | $4,480.63 | $0.00 |
| Equipment procurement | $15,682.21 | 100% | $15,682.21 | $7,056.99 | $8,625.22 |
| Assembly & wiring | $13,441.90 | 40% | $5,376.76 | $0.00 | $5,376.76 |
| FAT & testing | $6,720.95 | 0% | $0.00 | $0.00 | $0.00 |
| Delivery & commissioning | $4,480.63 | 0% | $0.00 | $0.00 | $0.00 |
| Total | $44,806.32 | 57% | $25,539.60 | $11,537.62 | $14,001.98 |
| Original contract value | $44,806.32 |
| Approved variations | $0.00 |
| Revised contract value | $44,806.32 |
| Claimed to date | $25,539.60 |
| Less previous claims | ($11,537.62) |
| This claim (ex GST) | $14,001.98 |
| Less retention (0%) | ($0.00) |
| GST 10% | $1,400.20 |
| Amount due (inc GST) | $15,402.18 |
| Balance remaining to claim | $19,266.72 |
Approved by John Lenoard on 02 Nov 2026.