Progress claim
PC-26-041-02
Claim no. 2
Period to 31 Oct 2026
Job J-26-041
Your order WCO-4500118822
Claim to
Wollombi Coal Operations Pty Ltd
Brett Kingsley
1240 Wollombi Road, Broke NSW 2330
ABN 23 145 882 610
Dual 75 kW VSD pump-control panel — Pit 3 dewatering — Pit 3 dewatering pump station
| Description | Contract value | % complete | Claimed to date | Previous claims | This claim |
|---|---|---|---|---|---|
| Design & drawings | $8,062.42 | 100% | $8,062.42 | $8,062.42 | $0.00 |
| Equipment procurement | $28,218.48 | 100% | $28,218.48 | $11,287.39 | $16,931.09 |
| Assembly & wiring | $24,187.27 | 45% | $10,884.27 | $0.00 | $10,884.27 |
| FAT & testing | $12,093.63 | 0% | $0.00 | $0.00 | $0.00 |
| Delivery & commissioning | $8,062.42 | 0% | $0.00 | $0.00 | $0.00 |
| V-01 — Add 4G telemetry RTU and third discharge pressure transmitter | $8,640.00 | 50% | $4,320.00 | $0.00 | $4,320.00 |
| Total | $89,264.22 | 57.7% | $51,485.17 | $19,349.81 | $32,135.36 |
| Original contract value | $80,624.22 |
| Approved variations | $8,640.00 |
| Revised contract value | $89,264.22 |
| Claimed to date | $51,485.17 |
| Less previous claims | ($19,349.81) |
| This claim (ex GST) | $32,135.36 |
| Less retention (0%) | ($0.00) |
| GST 10% | $3,213.54 |
| Amount due (inc GST) | $35,348.90 |
| Balance remaining to claim | $37,779.05 |