Hydra Power Solutions

J-26-041 · Dual 75 kW VSD pump-control panel — Pit 3 dewatering

Wollombi Coal Operations Pty Ltd · Pit 3 dewatering pump station
Xero · synced 07:30 Demo data 04 Nov 2026
J-26-041 In production Panel build
Quote Q-26-0172 Order parts (1)

Dual 75 kW VSD pump-control panel — Pit 3 dewatering

Job moneyex GST · labour at internal rates · committed = ordered, not yet received
Revenue
Quoted contract$80,624.22
Approved variations$8,640.00
Pending variations (not counted)$6,200.00
Revised contract$89,264.22
Claims & cash
Claimed to date$19,349.81
Invoiced$19,349.81
Paid$0.00
Overdue (inc GST)$21,284.79
Remaining to claim$69,914.41
Cost — budget vs actual
Labour 94.5 of 174 h$6,624 / $13,660
Materials received$41,704
Open purchase commitments$1,580
Materials budget (incl. variations)$49,244
Other allowance (subcontract, freight, hire)$3,000
Forecast cost at completion$65,904
Expected margin
26.2%
$23,360
Quoted at 25.7%
Cost to date $48,328 · 54% of labour hours used
Due 04 Dec 2026

Stages

Stage values $80,624 = contract
#StageContract valueDueStatusResponsible
1 Design & drawings $8,062.42 06 Oct 2026 In progress Daniel Reeves
2 Equipment procurement $28,218.48 21 Oct 2026 Complete Daniel Reeves
3 Assembly & wiring $24,187.27 04 Nov 2026 In progress Daniel Reeves
4 FAT & testing $12,093.63 19 Nov 2026 Not started Daniel Reeves
5 Delivery & commissioning $8,062.42 04 Dec 2026 Not started Daniel Reeves
TaskWhereStagePersonStartFinishEst hBooked h%Status
Drawings & IFC approval Office Design & drawings Amy Tran 21 Sep 2026 02 Oct 2026 30 31.5 100 Complete
Enclosure prep, gland plates & mounting rails Workshop Assembly & wiring Josh Bell 12 Oct 2026 16 Oct 2026 16 15.75 100 Complete
Mount drives, reactors & switchgear Workshop Assembly & wiring Ryan Cole 21 Oct 2026 30 Oct 2026 30 31.5 100 Complete
PLC & HMI programming Office Design & drawings Sam Whitaker 26 Oct 2026 13 Nov 2026 18 8.25 55 In production
Power wiring Workshop Assembly & wiring Ryan Cole 02 Nov 2026 10 Nov 2026 28 7.5 35 In production
Control wiring & PLC / HMI fit-off Workshop Assembly & wiring Tyler Nguyen 04 Nov 2026 13 Nov 2026 26 0 10 Awaiting materials
FAT & testing Workshop FAT & testing Luke Harding 16 Nov 2026 20 Nov 2026 14 0 0 Ready
Delivery & site commissioning — Pit 3 Site Delivery & commissioning Chris Walsh 30 Nov 2026 04 Dec 2026 24 0 0 Ready

Components

To order 1On order 1Arrived 38
Order outstanding
PartDescriptionQtyStockOrderedReceivedTo orderETAPONeeded forStatus
CBL-CTRL-12C Control cable 12C 1.5 mm² screened 60 0 60 60 0 — PO-26-0333 Power wiring Arrived
CBL-GLAND-M63 Cable gland kit M63, brass, c/w locknut 6 0 6 6 0 — PO-26-0333 Power wiring Arrived
RX-DIN-35 DIN rail 35 mm top-hat, 2 m length 4 0 4 4 0 — PO-26-0333 Power wiring Arrived
RX-DUCT-60 Slotted cable duct 60 × 60, 2 m 8 0 8 8 0 — PO-26-0333 Power wiring Arrived
RX-EARTH12 Copper earth bar, 12-way 1 0 1 1 0 — PO-26-0333 Power wiring Arrived
RX-FAN-150 Filter fan 230 V 150 m³/h c/w exhaust filter 2 0 2 2 0 — PO-26-0333 Power wiring Arrived
RX-FERR Bootlace ferrule kit, assorted 1 0 1 1 0 — PO-26-0333 Power wiring Arrived
RX-HEATER Anti-condensation heater 100 W 1 0 1 1 0 — PO-26-0333 Power wiring Arrived
RX-LIGHT Panel LED light c/w door switch 1 0 1 1 0 — PO-26-0333 Power wiring Arrived
RX-LUG-95 Compression lug 95 mm², pack of 10 2 0 2 2 0 — PO-26-0333 Power wiring Arrived
RX-TB-4 Terminal block 4 mm², box of 50 2 0 2 2 0 — PO-26-0333 Power wiring Arrived
RX-THERMO Enclosure thermostat / hygrostat 1 0 1 1 0 — PO-26-0333 Power wiring Arrived
RIT-PLINTH-1200 VX25 plinth 100 mm, 1200 W 1 0 1 1 0 — PO-26-0325 Enclosure prep, gland plates & mounting rails Arrived
RIT-VX-1812 Rittal VX25 freestanding 1800H × 1200W × 500D, 2-door 1 0 1 1 0 — PO-26-0325 Enclosure prep, gland plates & mounting rails Arrived
EH-FMX21 E+H Waterpilot FMX21 hydrostatic level 0–10 m, 20 m cable 1 0 1 1 0 — PO-26-0335 Control wiring & PLC / HMI fit-off Arrived
EH-PMC21 E+H Cerabar PMC21 pressure transmitter 0–16 bar, 4–20 mA 2 0 2 2 0 — PO-26-0335 Control wiring & PLC / HMI fit-off Arrived
EH-PMC21 E+H Cerabar PMC21 pressure transmitter 0–16 bar, 4–20 mA 1 0 2 2 0 — PO-26-0335 Control wiring & PLC / HMI fit-off Arrived
SE-ESW-8 Unmanaged industrial Ethernet switch, 8-port 1 0 1 1 0 — PO-26-0330 Control wiring & PLC / HMI fit-off Arrived
SE-HMIST6-7 Harmony ST6 7" touch HMI, Ethernet 1 0 1 0 0 12 Nov 2026 PO-26-0330 Control wiring & PLC / HMI fit-off Late
SE-PSU-24-10 24 VDC 10 A switch-mode power supply 1 0 1 1 0 — PO-26-0330 Control wiring & PLC / HMI fit-off Arrived
SE-RM17-PF Phase failure / sequence relay 1 0 1 1 0 — PO-26-0330 Control wiring & PLC / HMI fit-off Arrived
SE-TM241 Schneider Modicon M241 PLC, 24 I/O, Ethernet + CANopen 1 0 1 1 0 — PO-26-0330 Control wiring & PLC / HMI fit-off Arrived
SE-TM3AI4 Modicon TM3 4-channel analogue input module 1 0 1 1 0 — PO-26-0330 Control wiring & PLC / HMI fit-off Arrived
SE-TM3AQ2 Modicon TM3 2-channel analogue output module 1 0 1 1 0 — PO-26-0330 Control wiring & PLC / HMI fit-off Arrived
SE-TM3DI16 Modicon TM3 16-channel digital input module 2 0 2 2 0 — PO-26-0330 Control wiring & PLC / HMI fit-off Arrived
SE-TM3DQ16R Modicon TM3 16-channel relay output module 1 0 1 1 0 — PO-26-0330 Control wiring & PLC / HMI fit-off Arrived
SE-UPS-24 24 VDC DC-UPS module c/w 7 Ah battery 1 0 1 1 0 — PO-26-0330 Control wiring & PLC / HMI fit-off Arrived
TEL-RTU-4G 4G telemetry RTU c/w antenna & SIM tray 1 0 0 0 1 — — Control wiring & PLC / HMI fit-off To order
NHP-AMM-96 Analogue ammeter 96 mm c/w CT 2 0 2 2 0 — PO-26-0328 Power wiring Arrived
NHP-ESTOP E-stop 40 mm mushroom, twist release, c/w NC block 2 0 2 2 0 — PO-26-0328 Power wiring Arrived
NHP-MCB-6 MCB 1P 6 A C-curve, 6 kA 6 0 6 6 0 — PO-26-0328 Power wiring Arrived
NHP-MCCB-250 NHP 250 A 3P MCCB, 36 kA, electronic trip 2 0 2 2 0 — PO-26-0328 Power wiring Arrived
NHP-MCCB-400 NHP 400 A 3P main switch-disconnector, 50 kA 1 0 1 1 0 — PO-26-0328 Power wiring Arrived
NHP-PL-LED LED pilot light 24 V (red / green / amber) 6 0 6 6 0 — PO-26-0328 Power wiring Arrived
NHP-RLY-24 Control relay 24 VDC 4 C/O c/w base 14 0 14 14 0 — PO-26-0328 Power wiring Arrived
NHP-SEL-HOA Hand-Off-Auto 3-position selector switch 2 0 2 2 0 — PO-26-0328 Power wiring Arrived
NHP-SPD-3P Surge protection device 3P+N, 40 kA 1 0 1 1 0 — PO-26-0328 Power wiring Arrived
ABB-ACS580-75 ABB ACS580-01-145A-4 VSD 75 kW IP21 2 0 2 2 0 — PO-26-0323 Mount drives, reactors & switchgear Arrived
ABB-EMC-145 EMC/RFI filter 145 A 2 0 2 2 0 — PO-26-0323 Mount drives, reactors & switchgear Arrived
ABB-LR-145 Line reactor 145 A, 3-phase 2 0 2 2 0 — PO-26-0323 Mount drives, reactors & switchgear Arrived

Variations

Approved $8,640 · pending $6,200 — only approved variations are claimed
V-02316 stainless outdoor canopy over panel$6,200Submitted
No.VariationValueEst. costRaisedCustomer refApproved byStatus
V-01 Add 4G telemetry RTU and third discharge pressure transmitter $8,640.00 $5,960.00 09 Oct 2026 WCO-VO-031 Brett Kingsley (Wollombi) Approved
V-02 316 stainless outdoor canopy over panel $6,200.00 $4,350.00 28 Oct 2026 — — Submitted

Drawings & documents

Doc no.TitleTypeRevUploadedByKB

Time booked

Timesheets →
PersonHoursCost
Amy Tran31.5$2,457
Ryan Cole19.5$1,404
Josh Bell15.75$1,103
Ben Adams15.5$589
Sam Whitaker8.25$784
Tyler Nguyen4$288
TaskEst hBooked hCostLast
Drawings & IFC approval3031.5$2,4572 Oct
Enclosure prep, gland plates & mounting rails1615.75$1,10316 Oct
Mount drives, reactors & switchgear3031.5$1,74130 Oct
PLC & HMI programming188.25$7843 Nov
Power wiring287.5$5403 Nov

Progress claims

ClaimPeriod toClaimed to datePreviousThis claimInvoiceStatus