Hydra Power Solutions

J-26-031 · Transformer maintenance & oil sampling round — Pit 4 & CHPP

Ravensworth Ridge Mining Pty Ltd · Pit 4 dewatering
Xero · synced 07:30 Demo data 04 Nov 2026
J-26-031 On site Service
Quote Q-26-0154 Order parts

Transformer maintenance & oil sampling round — Pit 4 & CHPP

Job moneyex GST · labour at internal rates · committed = ordered, not yet received
Revenue
Quoted contract$39,140.00
Approved variations$0.00
Revised contract$39,140.00
Claims & cash
Claimed to date$29,746.40
Invoiced$29,746.40
Paid$22,114.10
Overdue (inc GST)$8,395.53
Remaining to claim$9,393.60
Cost — budget vs actual
Labour 191.2 of 242 h$13,006 / $19,136
Materials received$0
Open purchase commitments$0
Materials budget$0
Other allowance (subcontract, freight, hire)$7,100
Forecast cost at completion$26,236
Expected margin
33.0%
$12,904
Quoted at 33.0%
Cost to date $13,006 · 79% of labour hours used
Due 27 Nov 2026

Stages

Stage values $39,140 = contract
#StageContract valueDueStatusResponsible
1 Planning & surveys $3,914.00 01 Sep 2026 Complete Daniel Reeves
2 Materials & preparation $11,742.00 30 Sep 2026 Not started Daniel Reeves
3 Site works $17,613.00 29 Oct 2026 In progress Daniel Reeves
4 Reports & handover $5,871.00 27 Nov 2026 Not started Daniel Reeves
TaskWhereStagePersonStartFinishEst hBooked h%Status
Survey & sampling plan Office Planning & surveys Amy Tran 03 Aug 2026 11 Aug 2026 17 4.65 100 Complete
Site round 1 — inspections & sampling Site Site works Chris Walsh 12 Aug 2026 23 Sep 2026 78 75.85 100 Complete
Breather & gasket refurbishment Workshop Site works Mick O'Connell 07 Sep 2026 05 Oct 2026 53 53.5 100 Complete
Site round 2 — maintenance Site Site works Tyler Nguyen 06 Oct 2026 17 Nov 2026 78 57.2 70 In production
Condition reports & handover Office Reports & handover Sam Whitaker 18 Nov 2026 26 Nov 2026 17 0 0 Ready

Components

To order 0On order 0Arrived 0
Order outstanding
PartDescriptionQtyStockOrderedReceivedTo orderETAPONeeded forStatus
Nothing here yet — use “Add component” to create the first one.

Variations

Approved $0 · pending $0 — only approved variations are claimed
No.VariationValueEst. costRaisedCustomer refApproved byStatus
Nothing here yet — use “Raise variation” to create the first one.

Drawings & documents

Doc no.TitleTypeRevUploadedByKB
Nothing here yet — use “Upload document” to create the first one.

Time booked

Timesheets →
PersonHoursCost
Tyler Nguyen57.2$4,118
Mick O'Connell53.5$3,745
Chris Walsh41.25$3,465
Ben Adams34.6$1,315
Amy Tran4.65$363
TaskEst hBooked hCostLast
Survey & sampling plan174.65$36311 Aug
Site round 1 — inspections & sampling7875.85$4,78023 Sep
Breather & gasket refurbishment5353.5$3,7455 Oct
Site round 2 — maintenance7857.2$4,1183 Nov

Progress claims

ClaimPeriod toClaimed to datePreviousThis claimInvoiceStatus