J-26-035 · Conveyor drive servicing & thermography — Q3/Q4

Kooragang Bulk Handling Pty Ltd · Berth K4 conveyor substation
Xero · synced 07:30 Demo data 04 Nov 2026
J-26-035 On site Service
Quote Q-26-0162 Order parts

Conveyor drive servicing & thermography — Q3/Q4

Job moneyex GST · labour at internal rates · committed = ordered, not yet received
Revenue
Quoted contract$34,120.00
Approved variations$0.00
Revised contract$34,120.00
Claims & cash
Claimed to date$22,092.70
Invoiced$22,092.70
Paid$12,368.50
Overdue (inc GST)$10,696.62
Remaining to claim$12,027.30
Cost — budget vs actual
Labour 133.7 of 256 h$8,983 / $20,608
Materials received$0
Open purchase commitments$0
Materials budget$0
Other allowance (subcontract, freight, hire)$1,200
Forecast cost at completion$21,808
Expected margin
36.1%
$12,312
Quoted at 36.1%
Cost to date $8,983 · 52% of labour hours used
Due 18 Dec 2026

Stages

Stage values $34,120 = contract
#StageContract valueDueStatusResponsible
1 Planning & surveys $3,412.00 28 Sep 2026 Not started Daniel Reeves
2 Materials & preparation $10,236.00 26 Oct 2026 Not started Daniel Reeves
3 Site works $15,354.00 23 Nov 2026 In progress Daniel Reeves
4 Reports & handover $5,118.00 18 Dec 2026 Not started Daniel Reeves
TaskWhereStagePersonStartFinishEst hBooked h%Status
Service plan & isolations list Office Site works Amy Tran 01 Sep 2026 07 Sep 2026 16 14 100 Complete
Round 1 — drives CV-1 to CV-8 Site Site works Tyler Nguyen 07 Sep 2026 19 Oct 2026 105 98.35 100 Complete
Round 2 — drives CV-9 to CV-16 Site Site works Ben Adams 26 Oct 2026 07 Dec 2026 108 21.3 25 In production
Thermography reports Office Site works Sam Whitaker 07 Dec 2026 17 Dec 2026 27 0 0 Ready

Components

To order 0On order 0Arrived 0
Order outstanding
PartDescriptionQtyStockOrderedReceivedTo orderETAPONeeded forStatus
Nothing here yet — use “Add component” to create the first one.

Variations

Approved $0 · pending $0 — only approved variations are claimed
No.VariationValueEst. costRaisedCustomer refApproved byStatus
Nothing here yet — use “Raise variation” to create the first one.

Drawings & documents

Doc no.TitleTypeRevUploadedByKB
Nothing here yet — use “Upload document” to create the first one.

Time booked

Timesheets →
PersonHoursCost
Tyler Nguyen98.35$7,081
Ben Adams21.3$809
Amy Tran14$1,092
TaskEst hBooked hCostLast
Service plan & isolations list1614$1,0927 Sep
Round 1 — drives CV-1 to CV-810598.35$7,08119 Oct
Round 2 — drives CV-9 to CV-1610821.3$8093 Nov

Progress claims

ClaimPeriod toClaimed to datePreviousThis claimInvoiceStatus