Job moneyex GST · labour at internal rates · committed = ordered, not yet received
Revenue
Quoted contract$86,328.86
Approved variations$0.00
Revised contract$86,328.86
Claims & cash
Claimed to date$86,328.86
Invoiced$86,328.86
Paid$86,328.86
Remaining to claim$0.00
Cost — budget vs actual
Labour 163 of 166 h$10,862 / $13,200
Materials received$50,974
Open purchase commitments$0
Materials budget$50,974
Other allowance (subcontract, freight, hire)$900
Forecast cost at completion$65,074
Expected margin
24.6%
$21,255
Quoted at 24.6%
Cost to date $61,836 · 98% of labour hours used
Due 11 Sep 2026
Stages
Stage values $86,329 = contract| # | Stage | Contract value | Due | Status | Responsible | |
|---|---|---|---|---|---|---|
| 1 | Design & drawings | $8,632.89 | 03 Jul 2026 | Complete | Daniel Reeves | |
| 2 | Equipment procurement | $30,215.10 | 20 Jul 2026 | Complete | Daniel Reeves | |
| 3 | Assembly & wiring | $25,898.66 | 07 Aug 2026 | Complete | Daniel Reeves | |
| 4 | FAT & testing | $12,949.33 | 24 Aug 2026 | Complete | Daniel Reeves | |
| 5 | Delivery & commissioning | $8,632.88 | 11 Sep 2026 | Complete | Daniel Reeves | |
Tasks
Open the schedule →| Task | Where | Stage | Person | Start | Finish | Est h | Booked h | % | Status | |
|---|---|---|---|---|---|---|---|---|---|---|
| Drawings & IFC approval | Office | Design & drawings | Amy Tran | 24 Jun 2026 | 30 Jun 2026 | 15 | 15.5 | 100 | Complete | |
| Enclosure prep & mounting | Workshop | Assembly & wiring | Josh Bell | 06 Jul 2026 | 13 Jul 2026 | 19 | 18.75 | 100 | Complete | |
| Mount & power wiring | Workshop | Assembly & wiring | Tyler Nguyen | 13 Jul 2026 | 03 Aug 2026 | 43 | 42 | 100 | Complete | |
| Control wiring & PLC | Workshop | Assembly & wiring | Ben Adams | 27 Jul 2026 | 13 Aug 2026 | 43 | 42 | 100 | Complete | |
| FAT & testing | Workshop | Delivery & commissioning | Luke Harding | 17 Aug 2026 | 24 Aug 2026 | 19 | 19.25 | 100 | Complete | |
| Delivery & commissioning | Site | Delivery & commissioning | Chris Walsh | 31 Aug 2026 | 10 Sep 2026 | 26 | 25.5 | 100 | Complete | |
Components
To order 0On order 0Arrived 35| Part | Description | Qty | Stock | Ordered | Received | To order | ETA | PO | Needed for | Status | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| CBL-GLAND-M63 | Cable gland kit M63, brass, c/w locknut | 6 | 0 | 6 | 6 | 0 | — | PO-26-0305 | Enclosure prep & mounting | Arrived | |
| RX-DIN-35 | DIN rail 35 mm top-hat, 2 m length | 2 | 0 | 2 | 2 | 0 | — | PO-26-0305 | Enclosure prep & mounting | Arrived | |
| RX-DUCT-60 | Slotted cable duct 60 × 60, 2 m | 4 | 0 | 4 | 4 | 0 | — | PO-26-0305 | Enclosure prep & mounting | Arrived | |
| RX-EARTH12 | Copper earth bar, 12-way | 1 | 0 | 1 | 1 | 0 | — | PO-26-0305 | Enclosure prep & mounting | Arrived | |
| RX-FAN-150 | Filter fan 230 V 150 m³/h c/w exhaust filter | 2 | 0 | 2 | 2 | 0 | — | PO-26-0305 | Enclosure prep & mounting | Arrived | |
| RX-FERR | Bootlace ferrule kit, assorted | 1 | 0 | 1 | 1 | 0 | — | PO-26-0305 | Enclosure prep & mounting | Arrived | |
| RX-HEATER | Anti-condensation heater 100 W | 1 | 0 | 1 | 1 | 0 | — | PO-26-0305 | Enclosure prep & mounting | Arrived | |
| RX-LIGHT | Panel LED light c/w door switch | 1 | 0 | 1 | 1 | 0 | — | PO-26-0305 | Enclosure prep & mounting | Arrived | |
| RX-TB-4 | Terminal block 4 mm², box of 50 | 2 | 0 | 2 | 2 | 0 | — | PO-26-0305 | Enclosure prep & mounting | Arrived | |
| RX-THERMO | Enclosure thermostat / hygrostat | 1 | 0 | 1 | 1 | 0 | — | PO-26-0305 | Enclosure prep & mounting | Arrived | |
| RIT-PLINTH-1200 | VX25 plinth 100 mm, 1200 W | 1 | 0 | 1 | 1 | 0 | — | PO-26-0300 | Enclosure prep & mounting | Arrived | |
| RIT-VX-1812 | Rittal VX25 freestanding 1800H × 1200W × 500D, 2-door | 1 | 0 | 1 | 1 | 0 | — | PO-26-0300 | Enclosure prep & mounting | Arrived | |
| EH-PMC21 | E+H Cerabar PMC21 pressure transmitter 0–16 bar, 4–20 mA | 2 | 0 | 2 | 2 | 0 | — | PO-26-0297 | Enclosure prep & mounting | Arrived | |
| HPV-PG-100 | Pressure gauge 100 mm 0–16 bar glycerine filled | 2 | 0 | 2 | 2 | 0 | — | PO-26-0308 | Enclosure prep & mounting | Arrived | |
| SE-ESW-8 | Unmanaged industrial Ethernet switch, 8-port | 1 | 0 | 1 | 1 | 0 | — | PO-26-0295 | Enclosure prep & mounting | Arrived | |
| SE-HMIST6-7 | Harmony ST6 7" touch HMI, Ethernet | 1 | 0 | 1 | 1 | 0 | — | PO-26-0295 | Enclosure prep & mounting | Arrived | |
| SE-PSU-24-10 | 24 VDC 10 A switch-mode power supply | 1 | 0 | 1 | 1 | 0 | — | PO-26-0295 | Enclosure prep & mounting | Arrived | |
| SE-TM241 | Schneider Modicon M241 PLC, 24 I/O, Ethernet + CANopen | 1 | 0 | 1 | 1 | 0 | — | PO-26-0295 | Enclosure prep & mounting | Arrived | |
| SE-TM3AI4 | Modicon TM3 4-channel analogue input module | 1 | 0 | 1 | 1 | 0 | — | PO-26-0295 | Enclosure prep & mounting | Arrived | |
| SE-TM3AQ2 | Modicon TM3 2-channel analogue output module | 1 | 0 | 1 | 1 | 0 | — | PO-26-0295 | Enclosure prep & mounting | Arrived | |
| SE-TM3DI16 | Modicon TM3 16-channel digital input module | 2 | 0 | 2 | 2 | 0 | — | PO-26-0295 | Enclosure prep & mounting | Arrived | |
| SE-TM3DQ16R | Modicon TM3 16-channel relay output module | 1 | 0 | 1 | 1 | 0 | — | PO-26-0295 | Enclosure prep & mounting | Arrived | |
| SE-UPS-24 | 24 VDC DC-UPS module c/w 7 Ah battery | 1 | 0 | 1 | 1 | 0 | — | PO-26-0295 | Enclosure prep & mounting | Arrived | |
| GF-CR32-4-15 | Grundfos CR 32-4 vertical multistage pump c/w 15 kW IE3 motor | 2 | 0 | 2 | 2 | 0 | — | PO-26-0293 | Enclosure prep & mounting | Arrived | |
| NHP-AMM-96 | Analogue ammeter 96 mm c/w CT | 2 | 0 | 2 | 2 | 0 | — | PO-26-0302 | Enclosure prep & mounting | Arrived | |
| NHP-MCB-6 | MCB 1P 6 A C-curve, 6 kA | 6 | 0 | 6 | 6 | 0 | — | PO-26-0302 | Enclosure prep & mounting | Arrived | |
| NHP-MCCB-100 | NHP 100 A 3P MCCB, 25 kA | 2 | 0 | 2 | 2 | 0 | — | PO-26-0302 | Enclosure prep & mounting | Arrived | |
| NHP-PL-LED | LED pilot light 24 V (red / green / amber) | 6 | 0 | 6 | 6 | 0 | — | PO-26-0302 | Enclosure prep & mounting | Arrived | |
| NHP-RLY-24 | Control relay 24 VDC 4 C/O c/w base | 12 | 0 | 12 | 12 | 0 | — | PO-26-0302 | Enclosure prep & mounting | Arrived | |
| NHP-SEL-HOA | Hand-Off-Auto 3-position selector switch | 2 | 0 | 2 | 2 | 0 | — | PO-26-0302 | Enclosure prep & mounting | Arrived | |
| ABB-ACS580-22 | ABB ACS580-01-046A-4 VSD 22 kW IP21 | 2 | 0 | 2 | 2 | 0 | — | PO-26-0291 | Enclosure prep & mounting | Arrived | |
| HPV-BFV150 | DN150 lugged butterfly valve, gear operated | 2 | 0 | 2 | 2 | 0 | — | PO-26-0308 | Enclosure prep & mounting | Arrived | |
| HPV-CHK150 | DN150 swing check valve, ductile iron | 2 | 0 | 2 | 2 | 0 | — | PO-26-0308 | Enclosure prep & mounting | Arrived | |
| HPV-GATE150 | DN150 resilient seat gate valve | 2 | 0 | 2 | 2 | 0 | — | PO-26-0308 | Enclosure prep & mounting | Arrived | |
| HPV-VIC77-150 | Victaulic Style 77 flexible coupling DN150 | 8 | 0 | 8 | 8 | 0 | — | PO-26-0308 | Enclosure prep & mounting | Arrived | |
Variations
Approved $0 · pending $0 — only approved variations are claimed| No. | Variation | Value | Est. cost | Raised | Customer ref | Approved by | Status |
|---|
Nothing here yet — use “Raise variation” to create the first one.
Drawings & documents
| Doc no. | Title | Type | Rev | Uploaded | By | KB |
|---|
Nothing here yet — use “Upload document” to create the first one.
Time booked
Timesheets →| Person | Hours | Cost |
|---|---|---|
| Ben Adams | 42 | $1,596 |
| Chris Walsh | 25.5 | $2,142 |
| Tyler Nguyen | 21.5 | $1,548 |
| Ryan Cole | 20.5 | $1,476 |
| Luke Harding | 19.25 | $1,579 |
| Josh Bell | 18.75 | $1,313 |
| Amy Tran | 15.5 | $1,209 |
| Task | Est h | Booked h | Cost | Last |
|---|---|---|---|---|
| Drawings & IFC approval | 15 | 15.5 | $1,209 | 30 Jun |
| Enclosure prep & mounting | 19 | 18.75 | $1,313 | 13 Jul |
| Mount & power wiring | 43 | 42 | $3,024 | 3 Aug |
| Control wiring & PLC | 43 | 42 | $1,596 | 13 Aug |
| FAT & testing | 19 | 19.25 | $1,579 | 24 Aug |
| Delivery & commissioning | 26 | 25.5 | $2,142 | 10 Sep |