J-26-029 · Process-water pressure boosting station

Barrington Gold Pty Ltd · Process water plant
Xero · synced 07:30 Demo data 04 Nov 2026
J-26-029 Complete Panel build
Quote Q-26-0151 Order parts

Process-water pressure boosting station

Job moneyex GST · labour at internal rates · committed = ordered, not yet received
Revenue
Quoted contract$86,328.86
Approved variations$0.00
Revised contract$86,328.86
Claims & cash
Claimed to date$86,328.86
Invoiced$86,328.86
Paid$86,328.86
Remaining to claim$0.00
Cost — budget vs actual
Labour 163 of 166 h$10,862 / $13,200
Materials received$50,974
Open purchase commitments$0
Materials budget$50,974
Other allowance (subcontract, freight, hire)$900
Forecast cost at completion$65,074
Expected margin
24.6%
$21,255
Quoted at 24.6%
Cost to date $61,836 · 98% of labour hours used
Due 11 Sep 2026

Stages

Stage values $86,329 = contract
#StageContract valueDueStatusResponsible
1 Design & drawings $8,632.89 03 Jul 2026 Complete Daniel Reeves
2 Equipment procurement $30,215.10 20 Jul 2026 Complete Daniel Reeves
3 Assembly & wiring $25,898.66 07 Aug 2026 Complete Daniel Reeves
4 FAT & testing $12,949.33 24 Aug 2026 Complete Daniel Reeves
5 Delivery & commissioning $8,632.88 11 Sep 2026 Complete Daniel Reeves
TaskWhereStagePersonStartFinishEst hBooked h%Status
Drawings & IFC approval Office Design & drawings Amy Tran 24 Jun 2026 30 Jun 2026 15 15.5 100 Complete
Enclosure prep & mounting Workshop Assembly & wiring Josh Bell 06 Jul 2026 13 Jul 2026 19 18.75 100 Complete
Mount & power wiring Workshop Assembly & wiring Tyler Nguyen 13 Jul 2026 03 Aug 2026 43 42 100 Complete
Control wiring & PLC Workshop Assembly & wiring Ben Adams 27 Jul 2026 13 Aug 2026 43 42 100 Complete
FAT & testing Workshop Delivery & commissioning Luke Harding 17 Aug 2026 24 Aug 2026 19 19.25 100 Complete
Delivery & commissioning Site Delivery & commissioning Chris Walsh 31 Aug 2026 10 Sep 2026 26 25.5 100 Complete

Components

To order 0On order 0Arrived 35
Order outstanding
PartDescriptionQtyStockOrderedReceivedTo orderETAPONeeded forStatus
CBL-GLAND-M63 Cable gland kit M63, brass, c/w locknut 6 0 6 6 0 — PO-26-0305 Enclosure prep & mounting Arrived
RX-DIN-35 DIN rail 35 mm top-hat, 2 m length 2 0 2 2 0 — PO-26-0305 Enclosure prep & mounting Arrived
RX-DUCT-60 Slotted cable duct 60 × 60, 2 m 4 0 4 4 0 — PO-26-0305 Enclosure prep & mounting Arrived
RX-EARTH12 Copper earth bar, 12-way 1 0 1 1 0 — PO-26-0305 Enclosure prep & mounting Arrived
RX-FAN-150 Filter fan 230 V 150 m³/h c/w exhaust filter 2 0 2 2 0 — PO-26-0305 Enclosure prep & mounting Arrived
RX-FERR Bootlace ferrule kit, assorted 1 0 1 1 0 — PO-26-0305 Enclosure prep & mounting Arrived
RX-HEATER Anti-condensation heater 100 W 1 0 1 1 0 — PO-26-0305 Enclosure prep & mounting Arrived
RX-LIGHT Panel LED light c/w door switch 1 0 1 1 0 — PO-26-0305 Enclosure prep & mounting Arrived
RX-TB-4 Terminal block 4 mm², box of 50 2 0 2 2 0 — PO-26-0305 Enclosure prep & mounting Arrived
RX-THERMO Enclosure thermostat / hygrostat 1 0 1 1 0 — PO-26-0305 Enclosure prep & mounting Arrived
RIT-PLINTH-1200 VX25 plinth 100 mm, 1200 W 1 0 1 1 0 — PO-26-0300 Enclosure prep & mounting Arrived
RIT-VX-1812 Rittal VX25 freestanding 1800H × 1200W × 500D, 2-door 1 0 1 1 0 — PO-26-0300 Enclosure prep & mounting Arrived
EH-PMC21 E+H Cerabar PMC21 pressure transmitter 0–16 bar, 4–20 mA 2 0 2 2 0 — PO-26-0297 Enclosure prep & mounting Arrived
HPV-PG-100 Pressure gauge 100 mm 0–16 bar glycerine filled 2 0 2 2 0 — PO-26-0308 Enclosure prep & mounting Arrived
SE-ESW-8 Unmanaged industrial Ethernet switch, 8-port 1 0 1 1 0 — PO-26-0295 Enclosure prep & mounting Arrived
SE-HMIST6-7 Harmony ST6 7" touch HMI, Ethernet 1 0 1 1 0 — PO-26-0295 Enclosure prep & mounting Arrived
SE-PSU-24-10 24 VDC 10 A switch-mode power supply 1 0 1 1 0 — PO-26-0295 Enclosure prep & mounting Arrived
SE-TM241 Schneider Modicon M241 PLC, 24 I/O, Ethernet + CANopen 1 0 1 1 0 — PO-26-0295 Enclosure prep & mounting Arrived
SE-TM3AI4 Modicon TM3 4-channel analogue input module 1 0 1 1 0 — PO-26-0295 Enclosure prep & mounting Arrived
SE-TM3AQ2 Modicon TM3 2-channel analogue output module 1 0 1 1 0 — PO-26-0295 Enclosure prep & mounting Arrived
SE-TM3DI16 Modicon TM3 16-channel digital input module 2 0 2 2 0 — PO-26-0295 Enclosure prep & mounting Arrived
SE-TM3DQ16R Modicon TM3 16-channel relay output module 1 0 1 1 0 — PO-26-0295 Enclosure prep & mounting Arrived
SE-UPS-24 24 VDC DC-UPS module c/w 7 Ah battery 1 0 1 1 0 — PO-26-0295 Enclosure prep & mounting Arrived
GF-CR32-4-15 Grundfos CR 32-4 vertical multistage pump c/w 15 kW IE3 motor 2 0 2 2 0 — PO-26-0293 Enclosure prep & mounting Arrived
NHP-AMM-96 Analogue ammeter 96 mm c/w CT 2 0 2 2 0 — PO-26-0302 Enclosure prep & mounting Arrived
NHP-MCB-6 MCB 1P 6 A C-curve, 6 kA 6 0 6 6 0 — PO-26-0302 Enclosure prep & mounting Arrived
NHP-MCCB-100 NHP 100 A 3P MCCB, 25 kA 2 0 2 2 0 — PO-26-0302 Enclosure prep & mounting Arrived
NHP-PL-LED LED pilot light 24 V (red / green / amber) 6 0 6 6 0 — PO-26-0302 Enclosure prep & mounting Arrived
NHP-RLY-24 Control relay 24 VDC 4 C/O c/w base 12 0 12 12 0 — PO-26-0302 Enclosure prep & mounting Arrived
NHP-SEL-HOA Hand-Off-Auto 3-position selector switch 2 0 2 2 0 — PO-26-0302 Enclosure prep & mounting Arrived
ABB-ACS580-22 ABB ACS580-01-046A-4 VSD 22 kW IP21 2 0 2 2 0 — PO-26-0291 Enclosure prep & mounting Arrived
HPV-BFV150 DN150 lugged butterfly valve, gear operated 2 0 2 2 0 — PO-26-0308 Enclosure prep & mounting Arrived
HPV-CHK150 DN150 swing check valve, ductile iron 2 0 2 2 0 — PO-26-0308 Enclosure prep & mounting Arrived
HPV-GATE150 DN150 resilient seat gate valve 2 0 2 2 0 — PO-26-0308 Enclosure prep & mounting Arrived
HPV-VIC77-150 Victaulic Style 77 flexible coupling DN150 8 0 8 8 0 — PO-26-0308 Enclosure prep & mounting Arrived

Variations

Approved $0 · pending $0 — only approved variations are claimed
No.VariationValueEst. costRaisedCustomer refApproved byStatus
Nothing here yet — use “Raise variation” to create the first one.

Drawings & documents

Doc no.TitleTypeRevUploadedByKB
Nothing here yet — use “Upload document” to create the first one.

Time booked

Timesheets →
PersonHoursCost
Ben Adams42$1,596
Chris Walsh25.5$2,142
Tyler Nguyen21.5$1,548
Ryan Cole20.5$1,476
Luke Harding19.25$1,579
Josh Bell18.75$1,313
Amy Tran15.5$1,209
TaskEst hBooked hCostLast
Drawings & IFC approval1515.5$1,20930 Jun
Enclosure prep & mounting1918.75$1,31313 Jul
Mount & power wiring4342$3,0243 Aug
Control wiring & PLC4342$1,59613 Aug
FAT & testing1919.25$1,57924 Aug
Delivery & commissioning2625.5$2,14210 Sep

Progress claims

ClaimPeriod toClaimed to datePreviousThis claimInvoiceStatus