SPS-14 sewage pump station control upgrade
Job moneyex GST · labour at internal rates · committed = ordered, not yet received
Revenue
Quoted contract$34,330.50
Approved variations$0.00
Revised contract$34,330.50
Claims & cash
Claimed to date$0.00
Invoiced$0.00
Paid$0.00
Remaining to claim$34,330.50
Cost — budget vs actual
Labour 27.3 of 106 h$1,998 / $8,432
Materials received$7,125
Open purchase commitments$7,170
Materials budget$14,295
Other allowance (subcontract, freight, hire)$2,000
Forecast cost at completion$24,727
Expected margin
28.0%
$9,604
Quoted at 28.0%
Cost to date $9,123 · 26% of labour hours used
Due 11 Dec 2026
Stages
Stage values $34,331 = contract| # | Stage | Contract value | Due | Status | Responsible | |
|---|---|---|---|---|---|---|
| 1 | Design & drawings | $3,433.05 | 26 Oct 2026 | Complete | Sam Whitaker | |
| 2 | Equipment procurement | $12,015.68 | 05 Nov 2026 | Not started | Sam Whitaker | |
| 3 | Assembly & wiring | $10,299.15 | 17 Nov 2026 | In progress | Sam Whitaker | |
| 4 | FAT & testing | $5,149.58 | 30 Nov 2026 | Not started | Sam Whitaker | |
| 5 | Delivery & commissioning | $3,433.04 | 11 Dec 2026 | Not started | Sam Whitaker | |
Tasks
Open the schedule →| Task | Where | Stage | Person | Start | Finish | Est h | Booked h | % | Status | |
|---|---|---|---|---|---|---|---|---|---|---|
| Drawings & IFC approval | Office | Design & drawings | Amy Tran | 19 Oct 2026 | 22 Oct 2026 | 10 | 10 | 100 | Complete | |
| Enclosure prep & mounting | Workshop | Assembly & wiring | Josh Bell | 26 Oct 2026 | 30 Oct 2026 | 12 | 12.25 | 100 | Complete | |
| Mount & power wiring | Workshop | Assembly & wiring | Tyler Nguyen | 02 Nov 2026 | 13 Nov 2026 | 28 | 5 | 30 | In production | |
| Control wiring & PLC | Workshop | Assembly & wiring | Ben Adams | 09 Nov 2026 | 23 Nov 2026 | 28 | 0 | 0 | Ready | |
| FAT & testing | Workshop | Delivery & commissioning | Luke Harding | 23 Nov 2026 | 30 Nov 2026 | 12 | 0 | 0 | Ready | |
| Delivery & commissioning | Site | Delivery & commissioning | Chris Walsh | 03 Dec 2026 | 10 Dec 2026 | 17 | 0 | 0 | Ready | |
Components
To order 0On order 2Arrived 8| Part | Description | Qty | Stock | Ordered | Received | To order | ETA | PO | Needed for | Status | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| RIT-SS316-1210 | 316 stainless enclosure 1200 × 1000 × 400, IP66 | 1 | 0 | 1 | 0 | 0 | 06 Nov 2026 | PO-26-0345 | Enclosure prep & mounting | Late | |
| EH-FMX21 | E+H Waterpilot FMX21 hydrostatic level 0–10 m, 20 m cable | 1 | 0 | 1 | 1 | 0 | — | PO-26-0348 | Enclosure prep & mounting | Arrived | |
| EH-FTL-FLOAT | Level float switch, PP, 10 m cable | 2 | 0 | 2 | 2 | 0 | — | PO-26-0348 | Enclosure prep & mounting | Arrived | |
| SE-PSU-24-10 | 24 VDC 10 A switch-mode power supply | 1 | 0 | 1 | 1 | 0 | — | PO-26-0343 | Enclosure prep & mounting | Arrived | |
| SE-TM241 | Schneider Modicon M241 PLC, 24 I/O, Ethernet + CANopen | 1 | 0 | 1 | 1 | 0 | — | PO-26-0343 | Enclosure prep & mounting | Arrived | |
| SE-TM3AI4 | Modicon TM3 4-channel analogue input module | 1 | 0 | 1 | 1 | 0 | — | PO-26-0343 | Enclosure prep & mounting | Arrived | |
| TEL-RTU-4G | 4G telemetry RTU c/w antenna & SIM tray | 1 | 0 | 1 | 1 | 0 | — | PO-26-0353 | Enclosure prep & mounting | Arrived | |
| NHP-MCCB-100 | NHP 100 A 3P MCCB, 25 kA | 1 | 0 | 1 | 1 | 0 | — | PO-26-0350 | Enclosure prep & mounting | Arrived | |
| NHP-SEL-HOA | Hand-Off-Auto 3-position selector switch | 2 | 0 | 2 | 2 | 0 | — | PO-26-0350 | Enclosure prep & mounting | Arrived | |
| ABB-ACS580-11 | ABB ACS580-01-026A-4 VSD 11 kW IP21 | 2 | 0 | 2 | 0 | 0 | 11 Nov 2026 | PO-26-0358 | Enclosure prep & mounting | Late | |
Variations
Approved $0 · pending $0 — only approved variations are claimed| No. | Variation | Value | Est. cost | Raised | Customer ref | Approved by | Status |
|---|
Nothing here yet — use “Raise variation” to create the first one.
Drawings & documents
| Doc no. | Title | Type | Rev | Uploaded | By | KB |
|---|
Nothing here yet — use “Upload document” to create the first one.
Time booked
Timesheets →| Person | Hours | Cost |
|---|---|---|
| Josh Bell | 12.25 | $858 |
| Amy Tran | 10 | $780 |
| Tyler Nguyen | 2.5 | $180 |
| Ryan Cole | 2.5 | $180 |
| Task | Est h | Booked h | Cost | Last |
|---|---|---|---|---|
| Drawings & IFC approval | 10 | 10 | $780 | 22 Oct |
| Enclosure prep & mounting | 12 | 12.25 | $858 | 30 Oct |
| Mount & power wiring | 28 | 5 | $360 | 3 Nov |
Progress claims
| Claim | Period to | Claimed to date | Previous | This claim | Invoice | Status |
|---|---|---|---|---|---|---|
| No claims yet. | ||||||