1.5 MVA transformer overhaul & oil sampling — Sub 2
Job moneyex GST · labour at internal rates · committed = ordered, not yet received
Revenue
Quoted contract$32,750.00
Approved variations$0.00
Revised contract$32,750.00
Claims & cash
Claimed to date$0.00
Invoiced$0.00
Paid$0.00
Remaining to claim$32,750.00
Cost — budget vs actual
Labour 73.2 of 150 h$5,297 / $11,328
Materials received$0
Open purchase commitments$0
Materials budget$0
Other allowance (subcontract, freight, hire)$11,770
Forecast cost at completion$23,098
Expected margin
29.5%
$9,652
Quoted at 29.5%
Cost to date $5,297 · 49% of labour hours used
Due 25 Nov 2026
Stages
Stage values $32,750 = contract| # | Stage | Contract value | Due | Status | Responsible | |
|---|---|---|---|---|---|---|
| 1 | Strip & assess | $6,550.00 | 19 Oct 2026 | Not started | Daniel Reeves | |
| 2 | Parts & materials | $9,825.00 | 02 Nov 2026 | Not started | Daniel Reeves | |
| 3 | Overhaul & rebuild | $11,462.50 | 12 Nov 2026 | In progress | Daniel Reeves | |
| 4 | Test & return to site | $4,912.50 | 25 Nov 2026 | Not started | Daniel Reeves | |
Tasks
Open the schedule →| Task | Where | Stage | Person | Start | Finish | Est h | Booked h | % | Status | |
|---|---|---|---|---|---|---|---|---|---|---|
| Removal from site & transport | Site | Overhaul & rebuild | Chris Walsh | 05 Oct 2026 | 07 Oct 2026 | 9 | 11 | 100 | Complete | |
| Strip, inspect & assess | Workshop | Overhaul & rebuild | Luke Harding | 08 Oct 2026 | 19 Oct 2026 | 29 | 1.9 | 100 | Complete | |
| Core, winding & tap changer rebuild | Workshop | Overhaul & rebuild | Mick O'Connell | 19 Oct 2026 | 09 Nov 2026 | 69 | 60.25 | 80 | In production | |
| Oil fill, dry-out & electrical tests | Workshop | Test & return to site | Luke Harding | 10 Nov 2026 | 17 Nov 2026 | 24 | 0 | 0 | Ready | |
| Return to site & reconnection | Site | Test & return to site | Chris Walsh | 19 Nov 2026 | 24 Nov 2026 | 18 | 0 | 0 | Ready | |
Components
To order 0On order 0Arrived 0| Part | Description | Qty | Stock | Ordered | Received | To order | ETA | PO | Needed for | Status |
|---|
Nothing here yet — use “Add component” to create the first one.
Variations
Approved $0 · pending $0 — only approved variations are claimed| No. | Variation | Value | Est. cost | Raised | Customer ref | Approved by | Status |
|---|
Nothing here yet — use “Raise variation” to create the first one.
Drawings & documents
| Doc no. | Title | Type | Rev | Uploaded | By | KB |
|---|
Nothing here yet — use “Upload document” to create the first one.
Time booked
Timesheets →| Person | Hours | Cost |
|---|---|---|
| Josh Bell | 31 | $2,170 |
| Mick O'Connell | 29.25 | $2,048 |
| Chris Walsh | 11 | $924 |
| Luke Harding | 1.9 | $156 |
| Task | Est h | Booked h | Cost | Last |
|---|---|---|---|---|
| Removal from site & transport | 9 | 11 | $924 | 7 Oct |
| Strip, inspect & assess | 29 | 1.9 | $156 | 16 Oct |
| Core, winding & tap changer rebuild | 69 | 60.25 | $4,218 | 3 Nov |
Progress claims
| Claim | Period to | Claimed to date | Previous | This claim | Invoice | Status |
|---|---|---|---|---|---|---|
| No claims yet. | ||||||