J-26-040 · Wash plant fibre optic backbone & PLC network

Hexham Industrial Maintenance · Hexham wash plant
Xero · synced 07:30 Demo data 04 Nov 2026
J-26-040 Planning Installation
Quote Q-26-0176 Order parts (3)

Wash plant fibre optic backbone & PLC network

Job moneyex GST · labour at internal rates · committed = ordered, not yet received
Revenue
Quoted contract$31,694.00
Approved variations$0.00
Revised contract$31,694.00
Claims & cash
Claimed to date$0.00
Invoiced$0.00
Paid$0.00
Remaining to claim$31,694.00
Cost — budget vs actual
Labour 0 of 114 h$0 / $9,444
Materials received$0
Open purchase commitments$0
Materials budget$3,680
Other allowance (subcontract, freight, hire)$9,700
Forecast cost at completion$22,824
Expected margin
28.0%
$8,870
Quoted at 28.0%
Cost to date $0 · 0% of labour hours used
Due 18 Dec 2026

Stages

Stage values $31,694 = contract
#StageContract valueDueStatusResponsible
1 Design $4,754.10 24 Nov 2026 Not started Sam Whitaker
2 Materials $9,508.20 02 Dec 2026 Not started Sam Whitaker
3 Installation $12,677.60 10 Dec 2026 Not started Sam Whitaker
4 Testing & handover $4,754.10 18 Dec 2026 Not started Sam Whitaker
TaskWhereStagePersonStartFinishEst hBooked h%Status
Network design & drawings Office Design Amy Tran 16 Nov 2026 23 Nov 2026 19 0 0 Ready
Fibre installation & splicing Site Installation Chris Walsh 24 Nov 2026 09 Dec 2026 48 0 0 Ready
Switch panels & PLC network changes Workshop Installation Ben Adams 26 Nov 2026 04 Dec 2026 28 0 0 Awaiting materials
Testing & handover Site Testing & handover Sam Whitaker 14 Dec 2026 17 Dec 2026 19 0 0 Ready

Components

To order 3On order 0Arrived 0
Order outstanding
PartDescriptionQtyStockOrderedReceivedTo orderETAPONeeded forStatus
RIT-AX-760 Rittal AX wall-mount enclosure 760 × 760 × 300 2 0 0 0 2 — — Switch panels & PLC network changes To order
SE-ESW-8 Unmanaged industrial Ethernet switch, 8-port 4 0 0 0 4 — — Switch panels & PLC network changes To order
SE-PSU-24-10 24 VDC 10 A switch-mode power supply 4 0 0 0 4 — — Switch panels & PLC network changes To order

Variations

Approved $0 · pending $0 — only approved variations are claimed
No.VariationValueEst. costRaisedCustomer refApproved byStatus
Nothing here yet — use “Raise variation” to create the first one.

Drawings & documents

Doc no.TitleTypeRevUploadedByKB
Nothing here yet — use “Upload document” to create the first one.

Time booked

Timesheets →
PersonHoursCost
No time booked yet.
TaskEst hBooked hCostLast

Progress claims

ClaimPeriod toClaimed to datePreviousThis claimInvoiceStatus
No claims yet.