Wash plant fibre optic backbone & PLC network
Job moneyex GST · labour at internal rates · committed = ordered, not yet received
Revenue
Quoted contract$31,694.00
Approved variations$0.00
Revised contract$31,694.00
Claims & cash
Claimed to date$0.00
Invoiced$0.00
Paid$0.00
Remaining to claim$31,694.00
Cost — budget vs actual
Labour 0 of 114 h$0 / $9,444
Materials received$0
Open purchase commitments$0
Materials budget$3,680
Other allowance (subcontract, freight, hire)$9,700
Forecast cost at completion$22,824
Expected margin
28.0%
$8,870
Quoted at 28.0%
Cost to date $0 · 0% of labour hours used
Due 18 Dec 2026
Stages
Stage values $31,694 = contract| # | Stage | Contract value | Due | Status | Responsible | |
|---|---|---|---|---|---|---|
| 1 | Design | $4,754.10 | 24 Nov 2026 | Not started | Sam Whitaker | |
| 2 | Materials | $9,508.20 | 02 Dec 2026 | Not started | Sam Whitaker | |
| 3 | Installation | $12,677.60 | 10 Dec 2026 | Not started | Sam Whitaker | |
| 4 | Testing & handover | $4,754.10 | 18 Dec 2026 | Not started | Sam Whitaker | |
Tasks
Open the schedule →| Task | Where | Stage | Person | Start | Finish | Est h | Booked h | % | Status | |
|---|---|---|---|---|---|---|---|---|---|---|
| Network design & drawings | Office | Design | Amy Tran | 16 Nov 2026 | 23 Nov 2026 | 19 | 0 | 0 | Ready | |
| Fibre installation & splicing | Site | Installation | Chris Walsh | 24 Nov 2026 | 09 Dec 2026 | 48 | 0 | 0 | Ready | |
| Switch panels & PLC network changes | Workshop | Installation | Ben Adams | 26 Nov 2026 | 04 Dec 2026 | 28 | 0 | 0 | Awaiting materials | |
| Testing & handover | Site | Testing & handover | Sam Whitaker | 14 Dec 2026 | 17 Dec 2026 | 19 | 0 | 0 | Ready | |
Components
To order 3On order 0Arrived 0| Part | Description | Qty | Stock | Ordered | Received | To order | ETA | PO | Needed for | Status | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| RIT-AX-760 | Rittal AX wall-mount enclosure 760 × 760 × 300 | 2 | 0 | 0 | 0 | 2 | — | — | Switch panels & PLC network changes | To order | |
| SE-ESW-8 | Unmanaged industrial Ethernet switch, 8-port | 4 | 0 | 0 | 0 | 4 | — | — | Switch panels & PLC network changes | To order | |
| SE-PSU-24-10 | 24 VDC 10 A switch-mode power supply | 4 | 0 | 0 | 0 | 4 | — | — | Switch panels & PLC network changes | To order | |
Variations
Approved $0 · pending $0 — only approved variations are claimed| No. | Variation | Value | Est. cost | Raised | Customer ref | Approved by | Status |
|---|
Nothing here yet — use “Raise variation” to create the first one.
Drawings & documents
| Doc no. | Title | Type | Rev | Uploaded | By | KB |
|---|
Nothing here yet — use “Upload document” to create the first one.
Time booked
Timesheets →| Person | Hours | Cost |
|---|---|---|
| No time booked yet. | ||
| Task | Est h | Booked h | Cost | Last |
|---|
Progress claims
| Claim | Period to | Claimed to date | Previous | This claim | Invoice | Status |
|---|---|---|---|---|---|---|
| No claims yet. | ||||||