Hydra Power Solutions

Schedule

Workshop & site · 21 Sep 2026 – 09 Oct 2026
Xero · synced 07:30 Demo data 04 Nov 2026
iWho's on what, by day. Drag a task to another day or person. Red outlines are double-bookings; amber means the parts won't be here in time; grey is approved leave.
← Week This week Week → Over-booked Parts not here by start Leave Leave requested
Person
Mon21 Sep
Tue22 Sep
Wed23 Sep
Thu24 Sep
Fri25 Sep
Mon28 Sep
Tue29 Sep
Wed30 Sep
Thu1 Oct
Fri2 Oct
Mon5 Oct
Tue6 Oct
Wed7 Oct
Thu8 Oct
Fri9 Oct
Sam WhitakerElectrical / Project Engineer
Amy TranElectrical Drafter
Luke HardingWorkshop Supervisor
Annual leave
Ryan ColeElectrical Tradesperson
Tyler NguyenElectrical Tradesperson
J-26-031Site round 2 — maintenance
Ben AdamsApprentice Electrician (3rd yr)
Josh BellMechanical Fitter
J-26-032Rebuild — seals, bearings, impellers
Mick O'ConnellMechanical Fitter / Poly Welder
Chris WalshSite Supervisor