Waiting on materials6
J-26-042 Control panel build — 3 × VSD starters
Ryan Cole · RX-DIN-35 not ordered, RX-DUCT-60 not ordered, RX-FERR not ordered, RX-TB-4 not ordered, RIT-CANOPY not ordered, RIT-SS316-1210 not ordered, EH-FMX21 not ordered, EH-FTL-FLOAT not ordered, EH-PMC21 not ordered, EH-PROMAG-150 not ordered, SE-ESW-8 not ordered, SE-HMIST6-7 not ordered, SE-PSU-24-10 not ordered, SE-TM241 not ordered, SE-TM3AI4 not ordered, SE-TM3AQ2 not ordered, SE-TM3DI16 not ordered, SE-TM3DQ16R not ordered, SE-UPS-24 not ordered, TEL-RTU-4G not ordered, NHP-AMM-96 not ordered, NHP-MCB-6 not ordered, NHP-MCCB-100 not ordered, NHP-MCCB-250 not ordered, NHP-PL-LED not ordered, NHP-RLY-24 not ordered, NHP-SEL-HOA not ordered, NHP-SPD-3P not ordered, ABB-ACS580-22 due 11 Nov — starts 11 Nov
J-26-041 Control wiring & PLC / HMI fit-off
Tyler Nguyen · SE-HMIST6-7 due 12 Nov, TEL-RTU-4G not ordered — starts 4 Nov
J-26-042 Electrical install & cabling
Tyler Nguyen · CBL-16-4C not ordered, CBL-35-4C not ordered, CBL-INST-1PR not ordered — starts 23 Nov
J-26-040 Switch panels & PLC network changes
Ben Adams · RIT-AX-760 not ordered, SE-ESW-8 not ordered, SE-PSU-24-10 not ordered — starts 26 Nov
J-26-042 Mechanical install — pumps & manifold
Josh Bell · GF-CR45-3-22 due 27 Nov — starts 16 Nov
J-26-042 Pipe spool fabrication & poly welding
Mick O'Connell · HPV-ARV50 due 9 Nov, HPV-BFV150 due 9 Nov, HPV-BFV150-ACT due 9 Nov, HPV-CHK150 due 9 Nov, HPV-GATE150 due 9 Nov — starts 3 Nov
Clashes5
Ryan Cole — 9 Nov, 10 Nov, 11 Nov, 12 Nov, 13 Nov
(up to 11.4 h/day)J-26-041 Power wiring · J-26-036 Control wiring & PLC · J-26-042 Control panel build — 3 × VSD starters
Tyler Nguyen — 11 Nov, 12 Nov, 13 Nov
(up to 8.6 h/day)J-26-031 Site round 2 — maintenance · J-26-038 Mount & power wiring · J-26-041 Control wiring & PLC / HMI fit-off
Josh Bell — 16 Nov, 17 Nov, 18 Nov, 19 Nov
(up to 16.9 h/day)J-26-032 Test run & dispatch · J-26-042 Mechanical install — pumps & manifold
Mick O'Connell — 9 Nov
(up to 9.3 h/day)J-26-039 Core, winding & tap changer rebuild · J-26-042 Pipe spool fabrication & poly welding
Chris Walsh — 9 Nov, 24 Nov
(up to 10.9 h/day)J-26-037 Site installation · J-26-033 Delivery & commissioning · J-26-036 Delivery & commissioning · J-26-039 Return to site & reconnection · J-26-040 Fibre installation & splicing