Hydra Power Solutions

Print PC-26-029-01

Progress claim
Xero · synced 07:30 Demo data 04 Nov 2026
← PC-26-029-01
Hydra Power Solutions
Hydra Power Solutions Pty Ltd
5 Campbell Street, Tomago NSW 2322 · 1800 173 178 · info@hydrapowersolutions.com.au
ABN 62 631 448 207
Progress claim
PC-26-029-01
Claim no. 1
Period to 30 Jun 2026
Job J-26-029
Your order BGD-77104
Claim to
Barrington Gold Pty Ltd
Mark Ferris
Bowman River Road, Gloucester NSW 2422
ABN 14 603 228 517
Process-water pressure boosting station — Process water plant
DescriptionContract value% completeClaimed to datePrevious claimsThis claim
Design & drawings$8,632.89100%$8,632.89$0.00$8,632.89
Equipment procurement$30,215.1060%$18,129.06$0.00$18,129.06
Assembly & wiring$25,898.660%$0.00$0.00$0.00
FAT & testing$12,949.330%$0.00$0.00$0.00
Delivery & commissioning$8,632.880%$0.00$0.00$0.00
Total$86,328.8631%$26,761.95$0.00$26,761.95
Original contract value$86,328.86
Approved variations$0.00
Revised contract value$86,328.86
Claimed to date$26,761.95
Less previous claims($0.00)
This claim (ex GST)$26,761.95
Less retention (0%)($0.00)
GST 10%$2,676.20
Amount due (inc GST)$29,438.15
Balance remaining to claim$59,566.91
Approved by John Lenoard on 01 Jul 2026.