Hydra Power Solutions

PC-26-029-01 — progress claim 1

J-26-029 Process-water pressure boosting station · Barrington Gold Pty Ltd
Xero · synced 07:30 Demo data 04 Nov 2026
← Progress claims · J-26-029
Print / PDF
1
Claimed
Approved by John Lenoard · 01 Jul 2026
2
Invoiced
INV-2237 · 01 Jul 2026 · Xero Synced
3
Paid
$29,438.15 · 30 Jul 2026
Job
J-26-029 Process-water pressure boosting station
Customer
Barrington Gold Pty Ltd · Mark Ferris
Customer order no.
BGD-77104
Claim no.
1
Period to
30 Jun 2026
Status
Paid
#DescriptionContract value% completeClaimed to datePrevious claimsThis claim
1Design & drawings $8,632.89 100% $8,632.89 $0.00 $8,632.89
2Equipment procurement $30,215.10 60% $18,129.06 $0.00 $18,129.06
3Assembly & wiring $25,898.66 0% $0.00 $0.00 $0.00
4FAT & testing $12,949.33 0% $0.00 $0.00 $0.00
5Delivery & commissioning $8,632.88 0% $0.00 $0.00 $0.00
Original contract$86,328.8631%$26,761.95$0.00$26,761.95
Total$86,328.8631%$26,761.95$0.00$26,761.95
Original contract value$86,328.86
Approved variations$0.00
Revised contract value$86,328.86
Claimed to date$26,761.95
Less previous claims($0.00)
This claim (ex GST)$26,761.95
Less retention (0%)($0.00)
GST 10%$2,676.20
Amount due (inc GST)$29,438.15
Balance remaining to claim$59,566.91
Claims on this job
ClaimPeriodThis claimStatusInvoice
PC-26-029-0130 Jun 2026$26,761.95PaidINV-2237
PC-26-029-0231 Jul 2026$32,804.97PaidINV-2240
PC-26-029-0311 Sep 2026$26,761.94PaidINV-2246