PC-26-029-02 — progress claim 2

J-26-029 Process-water pressure boosting station · Barrington Gold Pty Ltd
Xero · synced 07:30 Demo data 04 Nov 2026
← Progress claims · J-26-029
Print / PDF
1
Claimed
Approved by John Lenoard · 03 Aug 2026
2
Invoiced
INV-2240 · 03 Aug 2026 · Xero Synced
3
Paid
$36,085.47 · 07 Sep 2026
Job
J-26-029 Process-water pressure boosting station
Customer
Barrington Gold Pty Ltd · Mark Ferris
Customer order no.
BGD-77104
Claim no.
2
Period to
31 Jul 2026
Status
Paid
#DescriptionContract value% completeClaimed to datePrevious claimsThis claim
1Design & drawings $8,632.89 100% $8,632.89 $8,632.89 $0.00
2Equipment procurement $30,215.10 100% $30,215.10 $18,129.06 $12,086.04
3Assembly & wiring $25,898.66 80% $20,718.93 $0.00 $20,718.93
4FAT & testing $12,949.33 0% $0.00 $0.00 $0.00
5Delivery & commissioning $8,632.88 0% $0.00 $0.00 $0.00
Original contract$86,328.8669%$59,566.92$26,761.95$32,804.97
Total$86,328.8669%$59,566.92$26,761.95$32,804.97
Original contract value$86,328.86
Approved variations$0.00
Revised contract value$86,328.86
Claimed to date$59,566.92
Less previous claims($26,761.95)
This claim (ex GST)$32,804.97
Less retention (0%)($0.00)
GST 10%$3,280.50
Amount due (inc GST)$36,085.47
Balance remaining to claim$26,761.94
Claims on this job
ClaimPeriodThis claimStatusInvoice
PC-26-029-0130 Jun 2026$26,761.95PaidINV-2237
PC-26-029-0231 Jul 2026$32,804.97PaidINV-2240
PC-26-029-0311 Sep 2026$26,761.94PaidINV-2246