Hydra Power Solutions

PC-26-029-03 — progress claim 3

J-26-029 Process-water pressure boosting station · Barrington Gold Pty Ltd
Xero · synced 07:30 Demo data 04 Nov 2026
← Progress claims · J-26-029
Print / PDF
1
Claimed
Approved by John Lenoard · 14 Sep 2026
2
Invoiced
INV-2246 · 14 Sep 2026 · Xero Synced
3
Paid
$29,438.13 · 19 Oct 2026
Job
J-26-029 Process-water pressure boosting station
Customer
Barrington Gold Pty Ltd · Mark Ferris
Customer order no.
BGD-77104
Claim no.
3
Period to
11 Sep 2026
Status
Paid
#DescriptionContract value% completeClaimed to datePrevious claimsThis claim
1Design & drawings $8,632.89 100% $8,632.89 $8,632.89 $0.00
2Equipment procurement $30,215.10 100% $30,215.10 $30,215.10 $0.00
3Assembly & wiring $25,898.66 100% $25,898.66 $20,718.93 $5,179.73
4FAT & testing $12,949.33 100% $12,949.33 $0.00 $12,949.33
5Delivery & commissioning $8,632.88 100% $8,632.88 $0.00 $8,632.88
Original contract$86,328.86100%$86,328.86$59,566.92$26,761.94
Total$86,328.86100%$86,328.86$59,566.92$26,761.94
Original contract value$86,328.86
Approved variations$0.00
Revised contract value$86,328.86
Claimed to date$86,328.86
Less previous claims($59,566.92)
This claim (ex GST)$26,761.94
Less retention (0%)($0.00)
GST 10%$2,676.19
Amount due (inc GST)$29,438.13
Balance remaining to claim$0.00
Claims on this job
ClaimPeriodThis claimStatusInvoice
PC-26-029-0130 Jun 2026$26,761.95PaidINV-2237
PC-26-029-0231 Jul 2026$32,804.97PaidINV-2240
PC-26-029-0311 Sep 2026$26,761.94PaidINV-2246