Hydra Power Solutions Pty Ltd
5 Campbell Street, Tomago NSW 2322 · 1800 173 178 · info@hydrapowersolutions.com.au
ABN 62 631 448 207
Progress claim
PC-26-029-03
Claim no. 3
Period to 11 Sep 2026
Job J-26-029
Your order BGD-77104
Claim to
Barrington Gold Pty Ltd
Mark Ferris
Bowman River Road, Gloucester NSW 2422
ABN 14 603 228 517
Process-water pressure boosting station — Process water plant
| Description | Contract value | % complete | Claimed to date | Previous claims | This claim |
|---|---|---|---|---|---|
| Design & drawings | $8,632.89 | 100% | $8,632.89 | $8,632.89 | $0.00 |
| Equipment procurement | $30,215.10 | 100% | $30,215.10 | $30,215.10 | $0.00 |
| Assembly & wiring | $25,898.66 | 100% | $25,898.66 | $20,718.93 | $5,179.73 |
| FAT & testing | $12,949.33 | 100% | $12,949.33 | $0.00 | $12,949.33 |
| Delivery & commissioning | $8,632.88 | 100% | $8,632.88 | $0.00 | $8,632.88 |
| Total | $86,328.86 | 100% | $86,328.86 | $59,566.92 | $26,761.94 |
| Original contract value | $86,328.86 |
| Approved variations | $0.00 |
| Revised contract value | $86,328.86 |
| Claimed to date | $86,328.86 |
| Less previous claims | ($59,566.92) |
| This claim (ex GST) | $26,761.94 |
| Less retention (0%) | ($0.00) |
| GST 10% | $2,676.19 |
| Amount due (inc GST) | $29,438.13 |
| Balance remaining to claim | $0.00 |
Approved by John Lenoard on 14 Sep 2026.
Power · Custom control systems · Pumping