Hydra Power Solutions

Print PC-26-029-02

Progress claim
Xero · synced 07:30 Demo data 04 Nov 2026
← PC-26-029-02
Hydra Power Solutions
Hydra Power Solutions Pty Ltd
5 Campbell Street, Tomago NSW 2322 · 1800 173 178 · info@hydrapowersolutions.com.au
ABN 62 631 448 207
Progress claim
PC-26-029-02
Claim no. 2
Period to 31 Jul 2026
Job J-26-029
Your order BGD-77104
Claim to
Barrington Gold Pty Ltd
Mark Ferris
Bowman River Road, Gloucester NSW 2422
ABN 14 603 228 517
Process-water pressure boosting station — Process water plant
DescriptionContract value% completeClaimed to datePrevious claimsThis claim
Design & drawings$8,632.89100%$8,632.89$8,632.89$0.00
Equipment procurement$30,215.10100%$30,215.10$18,129.06$12,086.04
Assembly & wiring$25,898.6680%$20,718.93$0.00$20,718.93
FAT & testing$12,949.330%$0.00$0.00$0.00
Delivery & commissioning$8,632.880%$0.00$0.00$0.00
Total$86,328.8669%$59,566.92$26,761.95$32,804.97
Original contract value$86,328.86
Approved variations$0.00
Revised contract value$86,328.86
Claimed to date$59,566.92
Less previous claims($26,761.95)
This claim (ex GST)$32,804.97
Less retention (0%)($0.00)
GST 10%$3,280.50
Amount due (inc GST)$36,085.47
Balance remaining to claim$26,761.94
Approved by John Lenoard on 03 Aug 2026.
Power · Custom control systems · Pumping