Hydra Power Solutions Pty Ltd
5 Campbell Street, Tomago NSW 2322 · 1800 173 178 · info@hydrapowersolutions.com.au
ABN 62 631 448 207
Progress claim
PC-26-032-03
Claim no. 3
Period to 31 Oct 2026
Job J-26-032
Your order BBD-0807
Claim to
Bowen Basin Dewatering Pty Ltd
Shane Keogh
8 Mill Street, Moranbah QLD 4744
ABN 29 618 774 330
Dewatering pumpset overhauls — 6 × Flygt 2640 — Moranbah yard
| Description | Contract value | % complete | Claimed to date | Previous claims | This claim |
|---|---|---|---|---|---|
| Strip & assess | $13,188.32 | 100% | $13,188.32 | $13,188.32 | $0.00 |
| Parts & materials | $19,782.48 | 100% | $19,782.48 | $19,782.48 | $0.00 |
| Overhaul & rebuild | $23,079.56 | 75% | $17,309.67 | $9,231.82 | $8,077.85 |
| Test & return to site | $9,891.24 | 0% | $0.00 | $0.00 | $0.00 |
| Total | $65,941.60 | 76.3% | $50,280.47 | $42,202.62 | $8,077.85 |
| Original contract value | $65,941.60 |
| Approved variations | $0.00 |
| Revised contract value | $65,941.60 |
| Claimed to date | $50,280.47 |
| Less previous claims | ($42,202.62) |
| This claim (ex GST) | $8,077.85 |
| Less retention (0%) | ($0.00) |
| GST 10% | $807.79 |
| Amount due (inc GST) | $8,885.64 |
| Balance remaining to claim | $15,661.13 |
Approved by John Lenoard on 02 Nov 2026.