1
Claimed
Approved by John Lenoard · 02 Nov 2026
2
Invoiced
INV-2262 · 02 Nov 2026 · Xero Synced
3
Paid
Due 01 Jan 2027
Job
J-26-032 Dewatering pumpset overhauls — 6 × Flygt 2640Customer
Bowen Basin Dewatering Pty Ltd · Shane KeoghCustomer order no.
BBD-0807Claim no.
3Period to
31 Oct 2026Status
Invoiced| # | Description | Contract value | % complete | Claimed to date | Previous claims | This claim |
|---|---|---|---|---|---|---|
| 1 | Strip & assess | $13,188.32 | 100% | $13,188.32 | $13,188.32 | $0.00 |
| 2 | Parts & materials | $19,782.48 | 100% | $19,782.48 | $19,782.48 | $0.00 |
| 3 | Overhaul & rebuild | $23,079.56 | 75% | $17,309.67 | $9,231.82 | $8,077.85 |
| 4 | Test & return to site | $9,891.24 | 0% | $0.00 | $0.00 | $0.00 |
| Original contract | $65,941.60 | 76.3% | $50,280.47 | $42,202.62 | $8,077.85 | |
| Total | $65,941.60 | 76.3% | $50,280.47 | $42,202.62 | $8,077.85 |
| Original contract value | $65,941.60 |
| Approved variations | $0.00 |
| Revised contract value | $65,941.60 |
| Claimed to date | $50,280.47 |
| Less previous claims | ($42,202.62) |
| This claim (ex GST) | $8,077.85 |
| Less retention (0%) | ($0.00) |
| GST 10% | $807.79 |
| Amount due (inc GST) | $8,885.64 |
| Balance remaining to claim | $15,661.13 |
Claims on this job
| Claim | Period | This claim | Status | Invoice |
|---|---|---|---|---|
| PC-26-032-01 | 31 Aug 2026 | $25,057.81 | Paid | INV-2245 |
| PC-26-032-02 | 30 Sep 2026 | $17,144.81 | Paid | INV-2253 |
| PC-26-032-03 | 31 Oct 2026 | $8,077.85 | Invoiced | INV-2262 |