Hydra Power Solutions

PC-26-032-01 — progress claim 1

J-26-032 Dewatering pumpset overhauls — 6 × Flygt 2640 · Bowen Basin Dewatering Pty Ltd
Xero · synced 07:30 Demo data 04 Nov 2026
← Progress claims · J-26-032
Print / PDF
1
Claimed
Approved by John Lenoard · 01 Sep 2026
2
Invoiced
INV-2245 · 01 Sep 2026 · Xero Synced
3
Paid
$27,563.59 · 30 Sep 2026
Job
J-26-032 Dewatering pumpset overhauls — 6 × Flygt 2640
Customer
Bowen Basin Dewatering Pty Ltd · Shane Keogh
Customer order no.
BBD-0807
Claim no.
1
Period to
31 Aug 2026
Status
Paid
#DescriptionContract value% completeClaimed to datePrevious claimsThis claim
1Strip & assess $13,188.32 100% $13,188.32 $0.00 $13,188.32
2Parts & materials $19,782.48 60% $11,869.49 $0.00 $11,869.49
3Overhaul & rebuild $23,079.56 0% $0.00 $0.00 $0.00
4Test & return to site $9,891.24 0% $0.00 $0.00 $0.00
Original contract$65,941.6038%$25,057.81$0.00$25,057.81
Total$65,941.6038%$25,057.81$0.00$25,057.81
Original contract value$65,941.60
Approved variations$0.00
Revised contract value$65,941.60
Claimed to date$25,057.81
Less previous claims($0.00)
This claim (ex GST)$25,057.81
Less retention (0%)($0.00)
GST 10%$2,505.78
Amount due (inc GST)$27,563.59
Balance remaining to claim$40,883.79
Claims on this job
ClaimPeriodThis claimStatusInvoice
PC-26-032-0131 Aug 2026$25,057.81PaidINV-2245
PC-26-032-0230 Sep 2026$17,144.81PaidINV-2253
PC-26-032-0331 Oct 2026$8,077.85InvoicedINV-2262