Hydra Power Solutions

PC-26-032-02 — progress claim 2

J-26-032 Dewatering pumpset overhauls — 6 × Flygt 2640 · Bowen Basin Dewatering Pty Ltd
Xero · synced 07:30 Demo data 04 Nov 2026
← Progress claims · J-26-032
Print / PDF
1
Claimed
Approved by John Lenoard · 01 Oct 2026
2
Invoiced
INV-2253 · 01 Oct 2026 · Xero Synced
3
Paid
$18,859.29 · 02 Nov 2026
Job
J-26-032 Dewatering pumpset overhauls — 6 × Flygt 2640
Customer
Bowen Basin Dewatering Pty Ltd · Shane Keogh
Customer order no.
BBD-0807
Claim no.
2
Period to
30 Sep 2026
Status
Paid
#DescriptionContract value% completeClaimed to datePrevious claimsThis claim
1Strip & assess $13,188.32 100% $13,188.32 $13,188.32 $0.00
2Parts & materials $19,782.48 100% $19,782.48 $11,869.49 $7,912.99
3Overhaul & rebuild $23,079.56 40% $9,231.82 $0.00 $9,231.82
4Test & return to site $9,891.24 0% $0.00 $0.00 $0.00
Original contract$65,941.6064%$42,202.62$25,057.81$17,144.81
Total$65,941.6064%$42,202.62$25,057.81$17,144.81
Original contract value$65,941.60
Approved variations$0.00
Revised contract value$65,941.60
Claimed to date$42,202.62
Less previous claims($25,057.81)
This claim (ex GST)$17,144.81
Less retention (0%)($0.00)
GST 10%$1,714.48
Amount due (inc GST)$18,859.29
Balance remaining to claim$23,738.98
Claims on this job
ClaimPeriodThis claimStatusInvoice
PC-26-032-0131 Aug 2026$25,057.81PaidINV-2245
PC-26-032-0230 Sep 2026$17,144.81PaidINV-2253
PC-26-032-0331 Oct 2026$8,077.85InvoicedINV-2262