Progress claim
PC-26-033-03
Claim no. 3
Period to 25 Sep 2026
Job J-26-033
Your order RRM-SC-1931
Claim to
Ravensworth Ridge Mining Pty Ltd
Hamish Doyle
Lemington Road, Ravensworth NSW 2330
ABN 61 155 330 902
Portable switchroom — Pit 4 dewatering — Pit 4 dewatering
| Description | Contract value | % complete | Claimed to date | Previous claims | This claim |
|---|---|---|---|---|---|
| Design & drawings | $20,378.35 | 100% | $20,378.35 | $20,378.35 | $0.00 |
| Equipment procurement | $71,324.24 | 100% | $71,324.24 | $49,926.97 | $21,397.27 |
| Assembly & wiring | $61,135.06 | 80% | $48,908.05 | $15,283.77 | $33,624.28 |
| FAT & testing | $30,567.53 | 20% | $6,113.51 | $0.00 | $6,113.51 |
| Delivery & commissioning | $20,378.36 | 0% | $0.00 | $0.00 | $0.00 |
| V-01 — Additional MCC tier — 2 × DOL starters for sump pumps | $14,200.00 | 100% | $14,200.00 | $7,100.00 | $7,100.00 |
| Total | $217,983.54 | 73.8% | $160,924.15 | $92,689.09 | $68,235.06 |
| Original contract value | $203,783.54 |
| Approved variations | $14,200.00 |
| Revised contract value | $217,983.54 |
| Claimed to date | $160,924.15 |
| Less previous claims | ($92,689.09) |
| This claim (ex GST) | $68,235.06 |
| Less retention (5%) | ($3,411.75) |
| GST 10% | $6,482.33 |
| Amount due (inc GST) | $71,305.64 |
| Balance remaining to claim | $57,059.39 |
Approved by John Lenoard on 28 Sep 2026.