PC-26-033-03 — progress claim 3

J-26-033 Portable switchroom — Pit 4 dewatering · Ravensworth Ridge Mining Pty Ltd
Xero · synced 07:30 Demo data 04 Nov 2026
← Progress claims · J-26-033
Print / PDF
1
Claimed
Approved by John Lenoard · 28 Sep 2026
2
Invoiced
INV-2248 · 28 Sep 2026 · Xero Synced
3
Paid
$71,305.64 · 01 Nov 2026
Job
J-26-033 Portable switchroom — Pit 4 dewatering
Customer
Ravensworth Ridge Mining Pty Ltd · Hamish Doyle
Customer order no.
RRM-SC-1931
Claim no.
3
Period to
25 Sep 2026
Status
Paid
#DescriptionContract value% completeClaimed to datePrevious claimsThis claim
1Design & drawings $20,378.35 100% $20,378.35 $20,378.35 $0.00
2Equipment procurement $71,324.24 100% $71,324.24 $49,926.97 $21,397.27
3Assembly & wiring $61,135.06 80% $48,908.05 $15,283.77 $33,624.28
4FAT & testing $30,567.53 20% $6,113.51 $0.00 $6,113.51
5Delivery & commissioning $20,378.36 0% $0.00 $0.00 $0.00
Original contract$203,783.5472%$146,724.15$85,589.09$61,135.06
Approved variations
VV-01 — Additional MCC tier — 2 × DOL starters for sump pumps $14,200.00 100% $14,200.00 $7,100.00 $7,100.00
Variations$14,200.00$14,200.00$7,100.00$7,100.00
Total$217,983.5473.8%$160,924.15$92,689.09$68,235.06
Original contract value$203,783.54
Approved variations$14,200.00
Revised contract value$217,983.54
Claimed to date$160,924.15
Less previous claims($92,689.09)
This claim (ex GST)$68,235.06
Less retention (5%)($3,411.75)
GST 10%$6,482.33
Amount due (inc GST)$71,305.64
Balance remaining to claim$57,059.39
Claims on this job
ClaimPeriodThis claimStatusInvoice
PC-26-033-0125 Jul 2026$34,643.20PaidINV-2239
PC-26-033-0225 Aug 2026$58,045.89PaidINV-2241
PC-26-033-0325 Sep 2026$68,235.06PaidINV-2248
PC-26-033-0425 Oct 2026$44,832.37InvoicedINV-2258