Hydra Power Solutions

PC-26-033-01 — progress claim 1

J-26-033 Portable switchroom — Pit 4 dewatering · Ravensworth Ridge Mining Pty Ltd
Xero · synced 07:30 Demo data 04 Nov 2026
← Progress claims · J-26-033
Print / PDF
1
Claimed
Approved by John Lenoard · 27 Jul 2026
2
Invoiced
INV-2239 · 27 Jul 2026 · Xero Synced
3
Paid
$36,202.14 · 25 Aug 2026
Job
J-26-033 Portable switchroom — Pit 4 dewatering
Customer
Ravensworth Ridge Mining Pty Ltd · Hamish Doyle
Customer order no.
RRM-SC-1931
Claim no.
1
Period to
25 Jul 2026
Status
Paid
#DescriptionContract value% completeClaimed to datePrevious claimsThis claim
1Design & drawings $20,378.35 100% $20,378.35 $0.00 $20,378.35
2Equipment procurement $71,324.24 20% $14,264.85 $0.00 $14,264.85
3Assembly & wiring $61,135.06 0% $0.00 $0.00 $0.00
4FAT & testing $30,567.53 0% $0.00 $0.00 $0.00
5Delivery & commissioning $20,378.36 0% $0.00 $0.00 $0.00
Original contract$203,783.5417%$34,643.20$0.00$34,643.20
Approved variations
VV-01 — Additional MCC tier — 2 × DOL starters for sump pumps $14,200.00 0% $0.00 $0.00 $0.00
Variations$14,200.00$0.00$0.00$0.00
Total$217,983.5415.9%$34,643.20$0.00$34,643.20
Original contract value$203,783.54
Approved variations$14,200.00
Revised contract value$217,983.54
Claimed to date$34,643.20
Less previous claims($0.00)
This claim (ex GST)$34,643.20
Less retention (5%)($1,732.16)
GST 10%$3,291.10
Amount due (inc GST)$36,202.14
Balance remaining to claim$183,340.34
Claims on this job
ClaimPeriodThis claimStatusInvoice
PC-26-033-0125 Jul 2026$34,643.20PaidINV-2239
PC-26-033-0225 Aug 2026$58,045.89PaidINV-2241
PC-26-033-0325 Sep 2026$68,235.06PaidINV-2248
PC-26-033-0425 Oct 2026$44,832.37InvoicedINV-2258