1
Claimed
Approved by John Lenoard · 26 Aug 2026
2
Invoiced
INV-2241 · 26 Aug 2026 · Xero Synced
3
Paid
$60,657.96 · 25 Sep 2026
Job
J-26-033 Portable switchroom — Pit 4 dewateringCustomer
Ravensworth Ridge Mining Pty Ltd · Hamish DoyleCustomer order no.
RRM-SC-1931Claim no.
2Period to
25 Aug 2026Status
Paid| # | Description | Contract value | % complete | Claimed to date | Previous claims | This claim |
|---|---|---|---|---|---|---|
| 1 | Design & drawings | $20,378.35 | 100% | $20,378.35 | $20,378.35 | $0.00 |
| 2 | Equipment procurement | $71,324.24 | 70% | $49,926.97 | $14,264.85 | $35,662.12 |
| 3 | Assembly & wiring | $61,135.06 | 25% | $15,283.77 | $0.00 | $15,283.77 |
| 4 | FAT & testing | $30,567.53 | 0% | $0.00 | $0.00 | $0.00 |
| 5 | Delivery & commissioning | $20,378.36 | 0% | $0.00 | $0.00 | $0.00 |
| Original contract | $203,783.54 | 42% | $85,589.09 | $34,643.20 | $50,945.89 | |
| Approved variations | ||||||
| V | V-01 — Additional MCC tier — 2 × DOL starters for sump pumps | $14,200.00 | 50% | $7,100.00 | $0.00 | $7,100.00 |
| Variations | $14,200.00 | $7,100.00 | $0.00 | $7,100.00 | ||
| Total | $217,983.54 | 42.5% | $92,689.09 | $34,643.20 | $58,045.89 | |
| Original contract value | $203,783.54 |
| Approved variations | $14,200.00 |
| Revised contract value | $217,983.54 |
| Claimed to date | $92,689.09 |
| Less previous claims | ($34,643.20) |
| This claim (ex GST) | $58,045.89 |
| Less retention (5%) | ($2,902.29) |
| GST 10% | $5,514.36 |
| Amount due (inc GST) | $60,657.96 |
| Balance remaining to claim | $125,294.45 |
Claims on this job
| Claim | Period | This claim | Status | Invoice |
|---|---|---|---|---|
| PC-26-033-01 | 25 Jul 2026 | $34,643.20 | Paid | INV-2239 |
| PC-26-033-02 | 25 Aug 2026 | $58,045.89 | Paid | INV-2241 |
| PC-26-033-03 | 25 Sep 2026 | $68,235.06 | Paid | INV-2248 |
| PC-26-033-04 | 25 Oct 2026 | $44,832.37 | Invoiced | INV-2258 |