Hydra Power Solutions

PC-26-033-02 — progress claim 2

J-26-033 Portable switchroom — Pit 4 dewatering · Ravensworth Ridge Mining Pty Ltd
Xero · synced 07:30 Demo data 04 Nov 2026
← Progress claims · J-26-033
Print / PDF
1
Claimed
Approved by John Lenoard · 26 Aug 2026
2
Invoiced
INV-2241 · 26 Aug 2026 · Xero Synced
3
Paid
$60,657.96 · 25 Sep 2026
Job
J-26-033 Portable switchroom — Pit 4 dewatering
Customer
Ravensworth Ridge Mining Pty Ltd · Hamish Doyle
Customer order no.
RRM-SC-1931
Claim no.
2
Period to
25 Aug 2026
Status
Paid
#DescriptionContract value% completeClaimed to datePrevious claimsThis claim
1Design & drawings $20,378.35 100% $20,378.35 $20,378.35 $0.00
2Equipment procurement $71,324.24 70% $49,926.97 $14,264.85 $35,662.12
3Assembly & wiring $61,135.06 25% $15,283.77 $0.00 $15,283.77
4FAT & testing $30,567.53 0% $0.00 $0.00 $0.00
5Delivery & commissioning $20,378.36 0% $0.00 $0.00 $0.00
Original contract$203,783.5442%$85,589.09$34,643.20$50,945.89
Approved variations
VV-01 — Additional MCC tier — 2 × DOL starters for sump pumps $14,200.00 50% $7,100.00 $0.00 $7,100.00
Variations$14,200.00$7,100.00$0.00$7,100.00
Total$217,983.5442.5%$92,689.09$34,643.20$58,045.89
Original contract value$203,783.54
Approved variations$14,200.00
Revised contract value$217,983.54
Claimed to date$92,689.09
Less previous claims($34,643.20)
This claim (ex GST)$58,045.89
Less retention (5%)($2,902.29)
GST 10%$5,514.36
Amount due (inc GST)$60,657.96
Balance remaining to claim$125,294.45
Claims on this job
ClaimPeriodThis claimStatusInvoice
PC-26-033-0125 Jul 2026$34,643.20PaidINV-2239
PC-26-033-0225 Aug 2026$58,045.89PaidINV-2241
PC-26-033-0325 Sep 2026$68,235.06PaidINV-2248
PC-26-033-0425 Oct 2026$44,832.37InvoicedINV-2258