Hydra Power Solutions

PC-26-033-04 — progress claim 4

J-26-033 Portable switchroom — Pit 4 dewatering · Ravensworth Ridge Mining Pty Ltd
Xero · synced 07:30 Demo data 04 Nov 2026
← Progress claims · J-26-033
Print / PDF
1
Claimed
Approved by John Lenoard · 27 Oct 2026
2
Invoiced
INV-2258 · 27 Oct 2026 · Xero Synced
3
Paid
Due 06 Nov 2026
Job
J-26-033 Portable switchroom — Pit 4 dewatering
Customer
Ravensworth Ridge Mining Pty Ltd · Hamish Doyle
Customer order no.
RRM-SC-1931
Claim no.
4
Period to
25 Oct 2026
Status
Invoiced
#DescriptionContract value% completeClaimed to datePrevious claimsThis claim
1Design & drawings $20,378.35 100% $20,378.35 $20,378.35 $0.00
2Equipment procurement $71,324.24 100% $71,324.24 $71,324.24 $0.00
3Assembly & wiring $61,135.06 100% $61,135.06 $48,908.05 $12,227.01
4FAT & testing $30,567.53 100% $30,567.53 $6,113.51 $24,454.02
5Delivery & commissioning $20,378.36 40% $8,151.34 $0.00 $8,151.34
Original contract$203,783.5494%$191,556.52$146,724.15$44,832.37
Approved variations
VV-01 — Additional MCC tier — 2 × DOL starters for sump pumps $14,200.00 100% $14,200.00 $14,200.00 $0.00
Variations$14,200.00$14,200.00$14,200.00$0.00
Total$217,983.5494.4%$205,756.52$160,924.15$44,832.37
Original contract value$203,783.54
Approved variations$14,200.00
Revised contract value$217,983.54
Claimed to date$205,756.52
Less previous claims($160,924.15)
This claim (ex GST)$44,832.37
Less retention (5%)($2,241.62)
GST 10%$4,259.08
Amount due (inc GST)$46,849.83
Balance remaining to claim$12,227.02
Claims on this job
ClaimPeriodThis claimStatusInvoice
PC-26-033-0125 Jul 2026$34,643.20PaidINV-2239
PC-26-033-0225 Aug 2026$58,045.89PaidINV-2241
PC-26-033-0325 Sep 2026$68,235.06PaidINV-2248
PC-26-033-0425 Oct 2026$44,832.37InvoicedINV-2258