Pit 3 dewatering pumps — overhaul 4 × Flygt 2670
Job moneyex GST · labour at internal rates · committed = ordered, not yet received
Revenue
Quoted contract$55,800.00
Approved variations$0.00
Revised contract$55,800.00
Claims & cash
Claimed to date$55,800.00
Invoiced$55,800.00
Paid$55,800.00
Remaining to claim$0.00
Cost — budget vs actual
Labour 244.5 of 296 h$17,077 / $21,860
Materials received$0
Open purchase commitments$0
Materials budget$0
Other allowance (subcontract, freight, hire)$17,400
Forecast cost at completion$39,260
Expected margin
29.6%
$16,540
Quoted at 29.6%
Cost to date $17,077 · 83% of labour hours used
Due 16 Oct 2026
Stages
Stage values $55,800 = contract| # | Stage | Contract value | Due | Status | Responsible | |
|---|---|---|---|---|---|---|
| 1 | Strip & assess | $11,160.00 | 17 Aug 2026 | Complete | Daniel Reeves | |
| 2 | Parts & materials | $16,740.00 | 07 Sep 2026 | Complete | Daniel Reeves | |
| 3 | Overhaul & rebuild | $19,530.00 | 28 Sep 2026 | Complete | Daniel Reeves | |
| 4 | Test & return to site | $8,370.00 | 16 Oct 2026 | Complete | Daniel Reeves | |
Tasks
Open the schedule →| Task | Where | Stage | Person | Start | Finish | Est h | Booked h | % | Status | |
|---|---|---|---|---|---|---|---|---|---|---|
| Remove pumps from Pit 3 | Site | Overhaul & rebuild | Chris Walsh | 27 Jul 2026 | 31 Jul 2026 | 18 | 18 | 100 | Complete | |
| Strip, inspect & measure wear | Workshop | Overhaul & rebuild | Luke Harding | 03 Aug 2026 | 17 Aug 2026 | 58 | 61.35 | 100 | Complete | |
| Rebuild — seals, bearings, impellers | Workshop | Overhaul & rebuild | Josh Bell | 17 Aug 2026 | 30 Sep 2026 | 174 | 123.3 | 100 | Complete | |
| Test run & reinstall | Site | Test & return to site | Chris Walsh | 05 Oct 2026 | 15 Oct 2026 | 46 | 41.8 | 100 | Complete | |
Components
To order 0On order 0Arrived 0| Part | Description | Qty | Stock | Ordered | Received | To order | ETA | PO | Needed for | Status |
|---|
Nothing here yet — use “Add component” to create the first one.
Variations
Approved $0 · pending $0 — only approved variations are claimed| No. | Variation | Value | Est. cost | Raised | Customer ref | Approved by | Status |
|---|
Nothing here yet — use “Raise variation” to create the first one.
Drawings & documents
| Doc no. | Title | Type | Rev | Uploaded | By | KB |
|---|
Nothing here yet — use “Upload document” to create the first one.
Time booked
Timesheets →| Person | Hours | Cost |
|---|---|---|
| Josh Bell | 73.05 | $5,114 |
| Luke Harding | 61.35 | $5,031 |
| Chris Walsh | 59.8 | $5,023 |
| Ben Adams | 50.25 | $1,910 |
| Task | Est h | Booked h | Cost | Last |
|---|---|---|---|---|
| Remove pumps from Pit 3 | 18 | 18 | $1,512 | 31 Jul |
| Strip, inspect & measure wear | 58 | 61.35 | $5,031 | 17 Aug |
| Rebuild — seals, bearings, impellers | 174 | 123.3 | $7,023 | 30 Sep |
| Test run & reinstall | 46 | 41.8 | $3,511 | 15 Oct |