J-26-034 · Pit 3 dewatering pumps — overhaul 4 × Flygt 2670

Wollombi Coal Operations Pty Ltd · Pit 3 dewatering pump station
Xero · synced 07:30 Demo data 04 Nov 2026
J-26-034 Complete Overhaul
Quote Q-26-0160 Order parts

Pit 3 dewatering pumps — overhaul 4 × Flygt 2670

Job moneyex GST · labour at internal rates · committed = ordered, not yet received
Revenue
Quoted contract$55,800.00
Approved variations$0.00
Revised contract$55,800.00
Claims & cash
Claimed to date$55,800.00
Invoiced$55,800.00
Paid$55,800.00
Remaining to claim$0.00
Cost — budget vs actual
Labour 244.5 of 296 h$17,077 / $21,860
Materials received$0
Open purchase commitments$0
Materials budget$0
Other allowance (subcontract, freight, hire)$17,400
Forecast cost at completion$39,260
Expected margin
29.6%
$16,540
Quoted at 29.6%
Cost to date $17,077 · 83% of labour hours used
Due 16 Oct 2026

Stages

Stage values $55,800 = contract
#StageContract valueDueStatusResponsible
1 Strip & assess $11,160.00 17 Aug 2026 Complete Daniel Reeves
2 Parts & materials $16,740.00 07 Sep 2026 Complete Daniel Reeves
3 Overhaul & rebuild $19,530.00 28 Sep 2026 Complete Daniel Reeves
4 Test & return to site $8,370.00 16 Oct 2026 Complete Daniel Reeves
TaskWhereStagePersonStartFinishEst hBooked h%Status
Remove pumps from Pit 3 Site Overhaul & rebuild Chris Walsh 27 Jul 2026 31 Jul 2026 18 18 100 Complete
Strip, inspect & measure wear Workshop Overhaul & rebuild Luke Harding 03 Aug 2026 17 Aug 2026 58 61.35 100 Complete
Rebuild — seals, bearings, impellers Workshop Overhaul & rebuild Josh Bell 17 Aug 2026 30 Sep 2026 174 123.3 100 Complete
Test run & reinstall Site Test & return to site Chris Walsh 05 Oct 2026 15 Oct 2026 46 41.8 100 Complete

Components

To order 0On order 0Arrived 0
Order outstanding
PartDescriptionQtyStockOrderedReceivedTo orderETAPONeeded forStatus
Nothing here yet — use “Add component” to create the first one.

Variations

Approved $0 · pending $0 — only approved variations are claimed
No.VariationValueEst. costRaisedCustomer refApproved byStatus
Nothing here yet — use “Raise variation” to create the first one.

Drawings & documents

Doc no.TitleTypeRevUploadedByKB
Nothing here yet — use “Upload document” to create the first one.

Time booked

Timesheets →
PersonHoursCost
Josh Bell73.05$5,114
Luke Harding61.35$5,031
Chris Walsh59.8$5,023
Ben Adams50.25$1,910
TaskEst hBooked hCostLast
Remove pumps from Pit 31818$1,51231 Jul
Strip, inspect & measure wear5861.35$5,03117 Aug
Rebuild — seals, bearings, impellers174123.3$7,02330 Sep
Test run & reinstall4641.8$3,51115 Oct

Progress claims

ClaimPeriod toClaimed to datePreviousThis claimInvoiceStatus