Accepted 21 Jul 2026 — customer order WCO-4500117390. This quote is now job J-26-034. Changes from here are variations on the job.
Quote detailsAccepted
Wollombi Coal Operations Pty Ltd · 30 days EOM
Lines
| Item | Qty | Unit cost | Markup | Unit sell | Line ex GST | GM | |
|---|---|---|---|---|---|---|---|
| Labour | |||||||
| Workshop labour | 250 hr | $72.00 | 60% | $115.00 | $28,750.00 | 37.4% | |
| Site labour | 36 hr | $80.00 | 56% | $125.00 | $4,500.00 | 36% | |
| Project management | 10 hr | $98.00 | 58% | $155.00 | $1,550.00 | 36.8% | |
| Other costs | |||||||
| Flygt 2670 overhaul kits (4) | 1 lot | $11,800.00 | 20% | $14,200.00 | $14,200.00 | 16.9% | |
| Motor rewinds — 2 × 22 kW (subcontract) | 1 lot | $5,600.00 | 21% | $6,800.00 | $6,800.00 | 17.6% | |
Labour $34,800.00Other $21,000.00Labour hours 296
| Subtotal ex GST | $55,800.00 |
| GST 10% | $5,580.00 |
| Total inc GST | $61,380.00 |
| Cost | $39,260.00 |
| Gross margin | $16,540.00 · 29.6% |