Hydra Power Solutions

Q-26-0160 · Pit 3 dewatering pumps — overhaul 4 × Flygt 2670

Wollombi Coal Operations Pty Ltd · Overhaul · issued 06 Jul 2026
Xero · synced 07:30 Demo data 04 Nov 2026
Accepted 21 Jul 2026 — customer order WCO-4500117390. This quote is now job J-26-034. Changes from here are variations on the job.
Quote detailsAccepted
Lines
ItemQtyUnit costMarkupUnit sellLine ex GSTGM
Labour
Workshop labour 250 hr $72.00 60% $115.00 $28,750.00 37.4%
Site labour 36 hr $80.00 56% $125.00 $4,500.00 36%
Project management 10 hr $98.00 58% $155.00 $1,550.00 36.8%
Other costs
Flygt 2670 overhaul kits (4) 1 lot $11,800.00 20% $14,200.00 $14,200.00 16.9%
Motor rewinds — 2 × 22 kW (subcontract) 1 lot $5,600.00 21% $6,800.00 $6,800.00 17.6%
Labour $34,800.00Other $21,000.00Labour hours 296
Subtotal ex GST$55,800.00
GST 10%$5,580.00
Total inc GST$61,380.00
Cost$39,260.00
Gross margin$16,540.00 · 29.6%
Next step
$55,800.00 ex GST
29.6% gross margin
Open job J-26-034 Print / PDF
Record
Quote
Q-26-0160
Issued
06 Jul 2026
Valid until
05 Aug 2026
Owner
Daniel Reeves
Enquiry
ENQ-1412 Repeat customer · 24 Jun 2026
Customer PO
WCO-4500117390
Job
J-26-034
EmailsAll sent
Not emailed yet.
Internal notes