Hydra Power Solutions

J-26-036 · 4 × dewatering pumpset control panels (Flygt 2670)

Bowen Basin Dewatering Pty Ltd · Moranbah yard
Xero · synced 07:30 Demo data 04 Nov 2026
J-26-036 In production Panel build
Quote Q-26-0163 Order parts

4 × dewatering pumpset control panels (Flygt 2670)

Job moneyex GST · labour at internal rates · committed = ordered, not yet received
Revenue
Quoted contract$44,806.32
Approved variations$0.00
Revised contract$44,806.32
Claims & cash
Claimed to date$25,539.60
Invoiced$25,539.60
Paid$11,537.62
Remaining to claim$19,266.72
Cost — budget vs actual
Labour 56 of 122 h$4,069 / $9,300
Materials received$21,978
Open purchase commitments$0
Materials budget$21,978
Other allowance (subcontract, freight, hire)$1,850
Forecast cost at completion$33,128
Expected margin
26.1%
$11,678
Quoted at 26.1%
Cost to date $26,047 · 46% of labour hours used
Due 27 Nov 2026

Stages

Stage values $44,806 = contract
#StageContract valueDueStatusResponsible
1 Design & drawings $4,480.63 29 Sep 2026 Complete Sam Whitaker
2 Equipment procurement $15,682.21 14 Oct 2026 Not started Sam Whitaker
3 Assembly & wiring $13,441.90 28 Oct 2026 In progress Sam Whitaker
4 FAT & testing $6,720.95 12 Nov 2026 Not started Sam Whitaker
5 Delivery & commissioning $4,480.63 27 Nov 2026 Not started Sam Whitaker
TaskWhereStagePersonStartFinishEst hBooked h%Status
Drawings & IFC approval Office Design & drawings Amy Tran 21 Sep 2026 28 Sep 2026 11 10.75 100 Complete
Enclosure prep & mounting Workshop Assembly & wiring Josh Bell 30 Sep 2026 07 Oct 2026 14 14 100 Complete
Mount & power wiring Workshop Assembly & wiring Tyler Nguyen 08 Oct 2026 26 Oct 2026 32 31.25 100 Complete
FAT & testing Workshop Delivery & commissioning Luke Harding 05 Nov 2026 11 Nov 2026 14 0 0 Ready
Control wiring & PLC Workshop Assembly & wiring Ryan Cole 09 Nov 2026 13 Nov 2026 32 0 0 Ready
Delivery & commissioning Site Delivery & commissioning Chris Walsh 17 Nov 2026 26 Nov 2026 19 0 0 Ready

Components

To order 0On order 0Arrived 12
Order outstanding
PartDescriptionQtyStockOrderedReceivedTo orderETAPONeeded forStatus
RX-DIN-35 DIN rail 35 mm top-hat, 2 m length 4 0 4 4 0 — PO-26-0333 Enclosure prep & mounting Arrived
RX-DUCT-60 Slotted cable duct 60 × 60, 2 m 8 0 8 8 0 — PO-26-0333 Enclosure prep & mounting Arrived
RX-TB-4 Terminal block 4 mm², box of 50 4 0 4 4 0 — PO-26-0333 Enclosure prep & mounting Arrived
RIT-AX-760 Rittal AX wall-mount enclosure 760 × 760 × 300 4 0 4 4 0 — PO-26-0325 Enclosure prep & mounting Arrived
EH-FTL-FLOAT Level float switch, PP, 10 m cable 8 0 8 8 0 — PO-26-0335 Enclosure prep & mounting Arrived
SE-RM17-PF Phase failure / sequence relay 4 0 4 4 0 — PO-26-0330 Enclosure prep & mounting Arrived
NHP-AMM-96 Analogue ammeter 96 mm c/w CT 4 0 4 4 0 — PO-26-0328 Enclosure prep & mounting Arrived
NHP-MCCB-100 NHP 100 A 3P MCCB, 25 kA 4 0 4 4 0 — PO-26-0328 Enclosure prep & mounting Arrived
NHP-PL-LED LED pilot light 24 V (red / green / amber) 12 0 12 12 0 — PO-26-0328 Enclosure prep & mounting Arrived
NHP-RLY-24 Control relay 24 VDC 4 C/O c/w base 12 0 12 12 0 — PO-26-0328 Enclosure prep & mounting Arrived
NHP-SEL-HOA Hand-Off-Auto 3-position selector switch 4 0 4 4 0 — PO-26-0328 Enclosure prep & mounting Arrived
ABB-ACS580-22 ABB ACS580-01-046A-4 VSD 22 kW IP21 4 0 4 4 0 — PO-26-0323 Enclosure prep & mounting Arrived

Variations

Approved $0 · pending $0 — only approved variations are claimed
No.VariationValueEst. costRaisedCustomer refApproved byStatus
Nothing here yet — use “Raise variation” to create the first one.

Drawings & documents

Doc no.TitleTypeRevUploadedByKB
Nothing here yet — use “Upload document” to create the first one.

Time booked

Timesheets →
PersonHoursCost
Tyler Nguyen16$1,152
Ryan Cole15.25$1,098
Josh Bell14$980
Amy Tran10.75$839
TaskEst hBooked hCostLast
Drawings & IFC approval1110.75$83928 Sep
Enclosure prep & mounting1414$9807 Oct
Mount & power wiring3231.25$2,25026 Oct

Progress claims

ClaimPeriod toClaimed to datePreviousThis claimInvoiceStatus