Hydra Power Solutions

J-26-037 · Conveyor starter upgrade — CV-12 / CV-14

Kooragang Bulk Handling Pty Ltd · Berth K4 conveyor substation
Xero · synced 07:30 Demo data 04 Nov 2026
J-26-037 On site Installation
Quote Q-26-0165 Order parts

Conveyor starter upgrade — CV-12 / CV-14

Job moneyex GST · labour at internal rates · committed = ordered, not yet received
Revenue
Quoted contract$62,390.60
Approved variations$0.00
Revised contract$62,390.60
Claims & cash
Claimed to date$24,082.77
Invoiced$4,991.25
Paid$0.00
Overdue (inc GST)$5,490.38
Remaining to claim$38,307.83
Cost — budget vs actual
Labour 116.2 of 188 h$8,012 / $15,092
Materials received$26,420
Open purchase commitments$0
Materials budget$26,420
Other allowance (subcontract, freight, hire)$3,100
Forecast cost at completion$44,612
Expected margin
28.5%
$17,779
Quoted at 28.5%
Cost to date $34,432 · 62% of labour hours used
Due 20 Nov 2026

Stages

Stage values $62,391 = contract
#StageContract valueDueStatusResponsible
1 Site establishment $4,991.25 09 Oct 2026 Complete Daniel Reeves
2 Equipment supply $24,956.24 19 Oct 2026 Not started Daniel Reeves
3 Mechanical installation $13,725.93 30 Oct 2026 In progress Daniel Reeves
4 Electrical installation $11,230.31 09 Nov 2026 Not started Daniel Reeves
5 Commissioning & handover $7,486.87 20 Nov 2026 Not started Daniel Reeves
TaskWhereStagePersonStartFinishEst hBooked h%Status
Site survey Site Site establishment Chris Walsh 28 Sep 2026 30 Sep 2026 12 11.75 100 Complete
Drawings & scope Office Site establishment Amy Tran 30 Sep 2026 05 Oct 2026 23 18.8 100 Complete
Workshop prefabrication Workshop Mechanical installation Ben Adams 08 Oct 2026 19 Oct 2026 43 44.25 100 Complete
Site installation Site Mechanical installation Chris Walsh 20 Oct 2026 09 Nov 2026 74 41.4 80 In production
Commissioning & handover Site Commissioning & handover Sam Whitaker 10 Nov 2026 19 Nov 2026 35 0 0 Ready

Components

To order 0On order 0Arrived 6
Order outstanding
PartDescriptionQtyStockOrderedReceivedTo orderETAPONeeded forStatus
CBL-95-4C Cable 95 mm² 4C+E XLPE/PVC 0.6/1 kV 140 0 140 140 0 — PO-26-0353 Workshop prefabrication Arrived
CBL-CTRL-12C Control cable 12C 1.5 mm² screened 200 0 200 200 0 — PO-26-0353 Workshop prefabrication Arrived
RIT-VX-2008 Rittal VX25 freestanding 2000H × 800W × 600D 2 0 2 2 0 — PO-26-0340 Workshop prefabrication Arrived
NHP-CTR-115 AC3 115 A contactor, 240 VAC coil 2 0 2 2 0 — PO-26-0350 Workshop prefabrication Arrived
NHP-MCCB-250 NHP 250 A 3P MCCB, 36 kA, electronic trip 2 0 2 2 0 — PO-26-0350 Workshop prefabrication Arrived
ABB-PSTX105 ABB PSTX105-600-70 soft starter 55 kW 2 0 2 2 0 — PO-26-0337 Workshop prefabrication Arrived

Variations

Approved $0 · pending $0 — only approved variations are claimed
No.VariationValueEst. costRaisedCustomer refApproved byStatus
Nothing here yet — use “Raise variation” to create the first one.

Drawings & documents

Doc no.TitleTypeRevUploadedByKB
Nothing here yet — use “Upload document” to create the first one.

Time booked

Timesheets →
PersonHoursCost
Chris Walsh28.4$2,386
Tyler Nguyen24.75$1,782
Ben Adams22.5$855
Mick O'Connell21.75$1,523
Amy Tran18.8$1,466
TaskEst hBooked hCostLast
Site survey1211.75$98730 Sep
Drawings & scope2318.8$1,4665 Oct
Workshop prefabrication4344.25$2,37819 Oct
Site installation7441.4$3,1813 Nov

Progress claims

ClaimPeriod toClaimed to datePreviousThis claimInvoiceStatus