iHours against jobs and tasks, submitted weekly and approved by the supervisor. Labour costs feed straight into job costing at each person's internal rate.
← Week This week Week → Approved Approved by Luke Harding 21 Sep
Total 38 h of 38On jobs 38 hNon-job 0 h Cost at $38.00/h $1,444
Job / taskMon 14 SepTue 15 SepWed 16 SepThu 17 SepFri 18 SepSat 19 SepSun 20 SepTotalCost
J-26-031 Site round 1 — inspections & sampling 0.851.10.61.25 3.8$144
J-26-032 Rebuild — seals, bearings, impellers 0.35 0.35$13
J-26-033 Control wiring & PLC 6.756.577.66 33.85$1,286
Day total7.67.67.67.67.638$1,444

Entries

DateJobTaskHoursNotes
14 Sep 2026 J-26-033 Control wiring & PLC 6.75 —
14 Sep 2026 J-26-031 Site round 1 — inspections & sampling 0.85 —
15 Sep 2026 J-26-033 Control wiring & PLC 6.5 —
15 Sep 2026 J-26-031 Site round 1 — inspections & sampling 1.1 —
16 Sep 2026 J-26-033 Control wiring & PLC 7 —
16 Sep 2026 J-26-031 Site round 1 — inspections & sampling 0.6 —
17 Sep 2026 J-26-033 Control wiring & PLC 7.6 —
18 Sep 2026 J-26-033 Control wiring & PLC 6 —
18 Sep 2026 J-26-031 Site round 1 — inspections & sampling 1.25 —
18 Sep 2026 J-26-032 Rebuild — seals, bearings, impellers 0.35 —