Hydra Power Solutions

PC-26-031-02 — progress claim 2

J-26-031 Transformer maintenance & oil sampling round — Pit 4 & CHPP · Ravensworth Ridge Mining Pty Ltd
Xero · synced 07:30 Demo data 04 Nov 2026
← Progress claims · J-26-031
Print / PDF
1
Claimed
Approved by John Lenoard · 30 Sep 2026
2
Invoiced
INV-2251 · 30 Sep 2026 · Xero Synced
3
Paid
$10,978.77 · 04 Nov 2026
Job
J-26-031 Transformer maintenance & oil sampling round — Pit 4 & CHPP
Customer
Ravensworth Ridge Mining Pty Ltd · Hamish Doyle
Customer order no.
RRM-SC-1902
Claim no.
2
Period to
30 Sep 2026
Status
Paid
#DescriptionContract value% completeClaimed to datePrevious claimsThis claim
1Planning & surveys $3,914.00 100% $3,914.00 $3,914.00 $0.00
2Materials & preparation $11,742.00 80% $9,393.60 $4,696.80 $4,696.80
3Site works $17,613.00 50% $8,806.50 $3,522.60 $5,283.90
4Reports & handover $5,871.00 0% $0.00 $0.00 $0.00
Original contract$39,140.0056.5%$22,114.10$12,133.40$9,980.70
Total$39,140.0056.5%$22,114.10$12,133.40$9,980.70
Original contract value$39,140.00
Approved variations$0.00
Revised contract value$39,140.00
Claimed to date$22,114.10
Less previous claims($12,133.40)
This claim (ex GST)$9,980.70
Less retention (0%)($0.00)
GST 10%$998.07
Amount due (inc GST)$10,978.77
Balance remaining to claim$17,025.90
Claims on this job
ClaimPeriodThis claimStatusInvoice
PC-26-031-0131 Aug 2026$12,133.40PaidINV-2243
PC-26-031-0230 Sep 2026$9,980.70PaidINV-2251
PC-26-031-0331 Oct 2026$7,632.30InvoicedINV-2260